Temporary Road Closure - Boys Camp Road - 5/22/25 at 9:00PM - 5/23/25 at 5:00AM
The Town of Lake Lure is planning a temporary road closure on Boys Camp Road on Thursday, May 22, 2025, from the hours of 9:00 PM until 5:00 AM on Friday, May 23, 2025.
-
The purpose of the road closure is to replace a culvert pipe under the road.
-
We have scheduled the work time at night to minimize the impact to the community.
-
The road will be impassable during this project on Thursday, May 22, 2025, from the hours of 9:00 PM until 5:00 AM on Friday, May 23, 2025.
-
The goal will be to finish the project as quickly as possible so the road can reopen in the morning.
-
Note that the Lake Lure Fire Department and Police Department will stage emergency equipment (a fire engine and a police car) on the other side of the crossing in case they are needed.
Questions: For questions, please email Communincations@townoflakelure.com
Friday, 5/23/25 Update
The Town of Lake Lure, NC is pleased to report that the culvert pipe was successfully installed on Boys Camp Road.