Lake Lure Storm Recovery Updates and More - 8/20/25

Dredging in Washburn Marina

OVER 1 MILLION TONS OF SILT, SEDIMENTATION, AND DEBRIS REMOVED FROM LAKE LURE!

  • The US Army Corps of Engineers (USACE), under the direction of FEMA, has been overseeing the restoration of Lake Lure with the assistance of AshBritt Environmental and many local contractors.  
  • They have been working 7 days a week for 12 hours each day since October of 2024!
  • We can never thank all of these workers for what they have done to restore Lake Lure!  

 

HOW MUCH SILT AND DEBRIS HAVE BEEN REMOVED FROM LAKE LURE?  The US Army Corps of Engineers (USACE) has provided the following data on silt and debris removal from Lake Lure as of 8/16/25.

  • A total of 907,872 tons of silt/sediment have been removed from Lake Lure (46,506 tons in the last week alone).

  • A total of 97,240 cubic yards of debris has been removed from the waterway (No change on the subsurface debris right now because the water level is down so low we cannot bring it to shore.)

 

WHAT IS THE LAKE LEVEL? The Lake Level is at about 965 Mean Sea Level (MSL). (Full pond is 990.5 MSL) 

  • This is about 5 feet up from where it has been so contractors can begin getting into the coves to remove silt and debris. 

  • The lake levels remain lower than it has ever been since the lake was built in the mid 1920's.  

  • The new reservoir drain (completed in April 2025) allowed Town staff to lower the lake beyond the limits of the Tainter gates, which are normally used to control the lake level. 

  • The lake level will remain drawn down at this stage of the lake restoration. 

  • The photo below shows the silt and debris removal at Tryon Bay. 

Tyon Bay Dredging 081520

Tryon Bay Dredging

 

HOW LONG WILL THE LAKE BE DOWN?  We are unable to specify the length of the drawdown period as this is dependent upon the sedimentation and debris removal process being overseen by the USACE

  • When a change in the lake level is planned, it will be posted here. 
  • As you can see from this photo below, work in the Washburn Marina area is going strong. 

  • You may watch the high-speed video of the silt removal process here.

  • Throughout the lake drawdown, Town engineers and staff will be scheduling work and inspections on the dam and the sewer system.

 

Marina Dredging 082025

Washburn Marina (Normally Filled with Water and Boats)

 

WHY CAN'T WE ACCESS THE LAKE? The Town of Lake Lure and all businesses are open and welcoming visitors; however, the lake itself remains closed to all unauthorized personnel.  

  • Lake Lure is currently a Federal Work Site. 

  • Do not enter the lake or the lakebed for everyone's safety, and to avoid fines. 

 

WHERE DOES ALL THE SILT/DEBRIS GO?  The sand and the construction and demolition material are taken to the Republic Landfill in Union County, SC, out of an abundance of precaution.  

  • The vegetative material is taken to the area behind the Lake Lure Fire Department, where it is reduced. 

  • The mulch is hauled to a landfill in Canton, NC.  

 

HOW DO THEY KNOW WHERE DEBRIS IS LOCATED? The U.S. Army Corps of Engineers employed cutting-edge technology to revolutionize debris cleanup in western North Carolina. Drones equipped with cameras and LiDAR sensors help crews locate debris, verify loads, and speed up debris removal, all while maintaining the safety of recovery crews.

 

WHEN WILL THE LAKE REOPEN?   The lake restoration is a dynamic process. 

  • We do not have a definitive timeline for completion at this time. 

  • The Town of Lake Lure remains hopeful that we will be able to reopen the lake in 2026. 

 

BEYOND THE LAKE, HOW WAS THE TOWN IMPACTED BY HURRICANE HELENE? The impact to the Town of Lake Lure is unimaginable.

  • Unfortunately, Lake Lure’s nearly 100 year old utilities infrastructure (sanitary sewer systems and wastewater treatment plant); our dam; Town Hall, Welcome Center, and municipal buildings; the Washburn Marina and floating boardwalk, the lake itself; and surrounding roadways and vehicular bridges were also significantly damaged by the devastating hurricane and flooding. 

  • Town officials have been working with FEMA, applying for grants, working with local and state representatives to obtain funding, and utilizing existing capital from the small Town's budget to restore these vital resources. 

 

HOW HAS THE WATER IN LAKE LURE BEEN IMPACTED? Please see the attached water sample results from June 30, 3035. 

  • All results are within normal limits, except for a very slight turbidity elevation near the debris site.

  • This is expected, with all the construction taking place.  

  • You may review the updated spreadsheet, which illustrates all the water sample data received by the Town of Lake Lure. 

  • For questions, please contact Communications@townoflakelure.com

 

MORSE PARK TEMPORARILY CLOSED

To ensure the work can be completed safely and on schedule, Morse Park will be temporarily closed. 

  • We cannot provide a timeline for this project at this time, but weekly updates will be provided here.
  • The Town of Lake Lure understands the importance of Morse Park to our community, and we appreciate your patience during this temporary closure.
  • The Washburn Marina debris and sedimentation removal project is a critical component of our lake restoration, and completing it safely and efficiently will benefit everyone in the long run.

While Morse Park is temporarily closed, the following areas remain open for public use:

These amenities are in Lake Lure and are open to the public.

We sincerely apologize for any inconvenience and thank you for your cooperation and support as we work toward reopening the lake. For questions, please email Communications@townoflakelure.com.

 

IN THE NEWS

 

1) The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.

 

2)  Something to look forward to!  Allen Foiles and Mary Ann Myers with Asheville Tennis Association met with Town of Lake Lure Parks, Recreation, and Lake Director, Dana Bradley, on Thursday, August 14th to deliver a check for $19,000 to the Town for use on future tennis and pickleball courts. These funds were awarded as part of a grant from the Stars Serving Up Love funds and were distributed by Asheville Tennis Association Hurricane Relief Fund.

 

3) Asheville area officials take flood recovery lessons to Texas, including Mayor Carol Pritchett. (shown below) 

American Flood Coalition - Mayor Carol Pritchett and other officials

Meeting with local officials, they exchanged strategies for disaster preparedness and community resilience

By Dee Pridgen August 18, 2025 11:40 am

ASHEVILLE, N.C. (828newsNOW) — Leaders from Western North Carolina took their hard-earned flood recovery experience to Texas last week, meeting with local officials to help the Hill Country bounce back after July’s devastating storms.

The delegation included Asheville City Council member Maggie Ullman, Lake Lure Mayor Carol Pritchett, Marshall Mayor Aaron Haynie and Avery County Commission Vice Chairman Dennis Aldridge. Representing the Western North Carolina Recovery and Resilience Partnership, they met with Kerrville Mayor Joe Herring, Mayor Pro Tem Brenda Hughes and Kerr County Judge Rob Kelly to exchange strategies for disaster preparedness and community resilience.

“This was a somber and deeply reflective meeting, rooted in the shared devastation of lives lost to floods in both our communities,” Ullman said in a statement. “It reinforced that the best recovery starts long before the next storm. It’s about building relationships, planning together and investing in resilience now. When communities share what works — and what doesn’t — we all get stronger for the future.”

Officials highlighted key lessons from their visit: strong relationships speed recovery, preparedness is a daily practice, mental health is as critical as rebuilding infrastructure, learning from others prevents repeated mistakes and hope and community engagement drive lasting progress.

The WNC Partnership, supported by the American Flood Coalition, continues to collaborate regionally to share resources, advocate for flood-affected communities, and improve readiness at state and federal levels.

The American Flood Coalition is a nonpartisan network of cities, elected officials, military leaders, businesses and civic groups dedicated to addressing the growing threats of flooding, rising sea levels and severe storms.

 

4) Building back stronger: Partnership to get $20 million more for flood resiliency

By Sarah White sarah@themountaineer.com

Aug 16, 2025

Western North Carolina is getting $20 million more for recovery and resiliency in the wake of Helene, but can it lead to long-term change?  In June, the North Carolina General Assembly passed a Helene and wildfire recovery bill that allocated $20 million in grant funding to rebuild and prevent future floods. This means WNC communities will soon be able to use state funding to support projects both for recovery needs and flood mitigation.

Read more here.

 

5) Earthquake Reported in Western North Carolina Thursday Morning. The mountains of North Carolina were shaken with an earthquake Thursday morning 

Updated: 4:08 PM EDT Aug 14, 2025

North Carolina —

An earthquake shook the North Carolina mountains Thursday morning. According to the U.S. Geological Survey, the earthquake struck 4.4 miles north of Columbus, NC at 11:14 a.m. Thursday, August 14. Columbus is a town in Polk County with 994 residents. It is located about 15 miles from Hendersonville, NC.

Watch the newscast here. 

Earthquake

6) Beloved Lake Lure Flowering Bridge demolished due to damage from Hurricane Helene

 

Updated: 7:51 PM EDT Aug 18, 2025

Peyton Furtado

Watch the coverage here.

Flowering Bridge Story

LAKE LURE, N.C. —

Monday, crews started demolition on Lake Lure's Flowering Bridge after it was severely damaged during Hurricane Helene. The pedestrian bridge was a Lake Lure landmark symbol of the connection between the town and Chimney Rock.

"I still feel a little bit of a shock about it. You know, it is. It is very sad," said Becky Melton with the Lake Lure Flowering Bridge Organization. "It's really hard to see her go, but we're all resolved in, taking that inspiration that she gave us and going forward with new gardens."

The Flowering Bridge featured beautiful blooms and thriving plant life, bricks laid with love and for loved ones.

"Some people were engaged to be married on this bridge. People had, family reunions visiting each other and would come to the bridge," Melton said.

It was made of memories as much as concrete and it saved the town from a worse fate.

"It did protect the town, and it protected the river as much as it could. So, she gave her life for us," Melton said.

George Minges with the Army Corps of Engineers said it held back a quote, "Huge dam of debris 30 feet high over the bridge behind us, where that had caught everything."

The bridge, according to the city of Lake Lure, was irreparably damaged during Helene. Plans to replace it are prepared and the Lake Lure Flowering Bridge Organization has started fundraising.

As demo day hit the bridge running, the gardening club that kept it up was as resilient as some of their plants. They and the town are recovering with the help of a little beauty and a little hope.

The historic three-arch bridge was built in 1925 to connect the communities of Lake Lure and Chimney Rock. The bridge was decommissioned in 2011 and transformed into a symbolic landmark featuring a dozen themed gardens over a two year period.

* * * * * 

Note: There was a wealth of news coverage in the past week regarding the inevitable plan to take down the beloved Flowering Bridge following the devastation by Hurricane Helene.  We all remain heartbroken over the loss of this historic structure that was loved by everyone who ever had the good fortune to see it.  The following are just a couple of examples, but there are many online that you may reference here.

 

Lake Lure Flowering Bridge in it's prime

 

 

MEETING THE MARK

 

The following is a summary of the high-level meetings from the past week.

  • Town Council Storm Recovery Meeting: Town Council met with Town leaders to discuss and move forward the ongoing work of the storm recovery.  Updates are included throughout this report.

  • FEMA Meeting:  Town Officials continue to meet with FEMA Officials to advance the complex public assistance projects. 

  • Lake Lure/Chimney Rock Planning Meeting: Lake Lure, Chimney Rock Village, Chimney Rock State Park, Chamber of Hickory Nut Gorge, and Rutherford County Tourism Development Authority Officials met to plan events surrounding the anniversary of Hurricane Helene.  

  • Town Council Meeting: Town Council held the first meeting in the new temporary Town Hall space at The Landings. You may review the Meeting Summary hereUpdates are included throughout this report.

Town Council 081225

  • American Flood Coalition: Mayor Pritchett participated with the American Flood Coalition in a visit to Kerr County, Texas to offer support and guidance.   

  • Media: Town Officials participated in interviews with WSPA, Channel 7 about the status of Lake Lure after one year following Hurricane Helene.

  • Sewer System Meeting: Town officials met with engineers from LaBella Associated for the ongoing work to restore and rebuild the town's sewer system and to seek funding to support this effort. 

  • ICF Meeting: Lake Lure Town Officials met with ICF officials to discuss the progress, status, and information required for FEMA reimbursements.

  • Playground Planning Meeting: Town Officials and the Parks & Recreation Board met with KaBOOM team to plan the new playground equipment for Lake Lure. 

 

CELL TOWER

 

The cell tower site is off Boys Camp Road in the old campground. The location shifted 100 feet back to accommodate the change in the topography due to the storm. It will still be 125 feet from property lines and will be fenced in. The tower will be 195 feet tall and will be a sleek design. Construction for the tower is expected to begin this summer 2025.  

The Cell Tower is on track for August construction.  Due to the Helene damage delay, the tower applicants had to go back through the state and federal permitting process again.  The NC State Historical Preservation Office provided a quick approval and we are all looking forward to improved cell signals and 5G service! The tower applicants are still on track and confident of breaking ground in late July.  They were doing some preliminary sample drilling on the site this month!

Update 8/20/25: The project is moving forward. Tillman Construction owns the tower and AT&T is the primary vendor though there will be room for additional vendors. 

  • A custom mounting is being designed to elevate the equipment, including the generator. 

  • Construction is slated to begin 8/21/25.

  • Updates will be provided here.

 

DAM UPDATES

 

  • Reservoir Drain: The reservoir drain project at the dam has allowed the Town to lower the lake to 30 feet as planned for the ongoing lake restoration work.  The drain is closed at times if work is taking place behind the dam to ensure safety.  Otherwise, it is open to allow a flow of water in the river. 

  • Field Testing for Replacement Dam: Schnabel Engineering is overseeing a geotechnical subsurface investigation to support the design of the replacement dam at Lake Lure. 

    • Task 1 – Investigation Planning – Complete

    • Task 2 – Field Investigations

      • Geologic Mapping: Complete.
      • Surface Geophysics: Complete.
      • Down-hole Geophysics: Geophysical surveys performed in 14 borings to date. Geophysical surveys planned for four additional borings.
      • Geotechnical Drilling and Sampling: 16 borings have been drilled to date (14 have been backfilled, and two left open for geophysical testing). Field staff have been on site to oversee drilling operations, log subsurface conditions, and collect soil and rock samples for laboratory   testing. Drilling for the last two borings began on July 21, 2025.
      • Surveying: Boundary, site feature, and topographic data collection is complete. The remaining survey work includes locating the two remaining borings to be drilled. We have received a draft survey deliverable and are currently reviewing the content.
    • Task 3 - Laboratory Testing: Completed laboratory testing on rock samples collected from the first 14 borings. An additional  round of laboratory testing will be completed once the final two borings are completed. Completed laboratory testing on soil samples collected from the completed borings to evaluate their engineering properties.
    • Task 4 – Geotechnical Data Report and Design Considerations Memorandum: Have begun efforts on the Geotechnical Data Report (GDR). Reviewed all data collected to date (boring log data, geophysical data, laboratory data, etc.) for inclusion in the GDR. Once the GDR is complete, we will use the findings to prepare a Design Considerations Memorandum.
  • Tainter Gate Repairs: Schnabel Engineering conducted an inspection of the Tainter gates. Based on their findings, the Town Council approved a work order for the design of necessary repairs, including seal repair.  We anticipate this work being completed when lake levels come back up, potentially this winter. Schnabel Engineering is developing the scope of work, which includes the design of repairs to the dam’s concrete ogee (allows for uncontrolled flow over the top of the reservoir) and the installation of new rubber seals along the base of the Tainter gates.

  • Grant to Support Design for Replacement Dam: We hope to begin design work for the replacement dam in the fall of 2025. We are hoping to receive confirmation on a FEMA High Hazard Dam Grant to support the cost of this project. We should receive a confirmation on this funding in September when the Field Testing work is complete. 

  • Boom: Schnabel is designing a boom for the dam area.

  • Deep Water Ramp: A deep water ramp is being designed near the dam for Town use. 

  • River Restoration: Successfully completed the restoration of the river channel located below the dam, returning it to its pre-storm condition. This project was executed entirely by Town personnel utilizing rented equipment, resulting in substantial cost savings compared to the use of contracted services. In addition to restoring hydraulic function and stability to the area, this work enabled the timely resumption of vital coring operations at the dam.

  • Recognition: We are also proud to share that the Town has been selected to receive the 2025 Southeast Regional Dam Safety Award from the Association of State Dam Safety Officials (ASDSO). This recognition highlights the Town’s efforts on the Low-Level Outlet Project, its proactive response to Hurricane Helene, and its ongoing commitment to securing funding for a long-term dam solution.

 

SEWER SYSTEM UPDATES

 

  • Sewer Replacement Project: Town Officials met with LaBella Engineering to review current task orders and progress on the sewer replacement project. Upcoming phases for the sewer project were submitted to the NC Department of Environmental Quality (NC DEQ) for review in an Engineering Report/Environmental Information Document (ER/EID).  NCDEQ has provided initial comments and questions, which LaBella is actively addressing.

    • In preparation for upcoming phases of the project, the Town has also begun communicating with several residents to discuss potential easement needs.
    • The Town continues to work closely with the North Carolina Division of Water Infrastructure (NC DWI) and neighboring communities to pursue a grant that will fund a study on the potential impacts and benefits of a regionalized sewer system.
    • Additionally, the Town is collaborating with NC DWI to secure supplemental State Revolving Fund (SRF) financing, which is expected to include principal forgiveness.
  • Sewer System Maintenance: Public Services continues to work to maintain the larger sewer system.  Planning and design work will be proceeding in Sunset Cove, Tryon Bay, Snug Harbor, and Grey Logs Cove in anticipation of future funding.  The Town has applied for FEMA funding to support restoration of the system.  We are awaiting a decision regarding this request and updates will be provided as new information becomes available.   

  • Mainline Sewer Repair: Public services officials have addressed an ongoing issue with a mainline sewer segment, implementing necessary repairs to improve service. 

  • Washburn Tank Cover Replacement: Successfully completed the replacement of 20 water tank system lid, improving system integrity and safety.

    • The Town has been working with LaBella Associates to design and replace the 20,000-gallon tank cover for the Washburn Tank.
    • The Authorization to Construct was issued on December 7, 2023, following the Water Tank Reconditioning Plan approval on November 7, 2023.
    • Although the project experienced delays due to Tropical Storm Helene, progress has continued.
    • The engineer’s certification was issued, and a request for final approval was submitted to NCDEQ on June 17, 2025.
    • Water testing was completed and yielded satisfactory results.
    • Final approval from NCDEQ was issued on July 11, 2025, officially marking the project's completion.
  • West-end Sewer System: The work on the West End Sewer System Project began on 3/10/25.  This project remains a top priority to reestablish service for properties west of the Memorial Bridge that have been without utilities since Tropical Storm Helene.  The Town would like to extend our sincere apologies for the continued delay in the West End Sewer Restoration Project. The Town is making every effort to advance the project as efficiently and safely as possible.  Although we do not have a specific completion date at this time, current projections indicate that services will be restored during the month of August. While no additional delays are expected, there is always the possibility of unforeseen circumstances that could impact the timeline. In the event of any significant changes, impacted customers are personally notified. The Town remains committed to transparency and to minimizing disruption throughout the remainder of the project. Last week, a manhole was finished, laterals were installed.  A design is being completed for the new gravity line and a bi-pass may be utilized to facilitate completion of the project. Continued construction and coordination efforts on the West End Sewer Project, including sewer line installation and supporting infrastructure.

  • Lift Station: The system is operational and online

  • Waste Water Treatment Plant: The Waste Water Treatment Plant (WWTP) is operational but we have submitted a request to FEMA for a replacement treatment system. We are awaiting a decision regarding this request and hope to relocate the system out of the flood zone.

    • FEMA Public Assistance (PA) is working with the Town to move the permanent repairs for the Wastewater Treatment Plant (WWTP) forward as a Version 0 project, which allows the Town to receive funding for architectural and engineering (A&E) services.

    • A task order with LaBella was previously approved by Town Council, contingent upon FEMA funding.

    • Once this project is officially obligated, LaBella Associates will be able to proceed with the design work. It is the Town's position—and that of the engineers at LaBella Associates, that the appropriate permanent repair for the WWTP is a full replacement of the facility, rather than piecemeal repairs to the existing plant, which is not feasible.

  • Utility Locate Responses: Responded to 26 utility locate requests through the 811 system, ensuring safe excavation and infrastructure protection across multiple work zones.

  • Are we applying for grants to assist with expenses? Yes!  LaBella Associates are working with Town officials to prepare an application for the Helene Recovery State Revolving Fund (SRF), which offers the potential for up to $5 million in principal forgiveness, if awarded. The SRF is a program that provides low-interest loans for water and wastewater infrastructure projects. 

 

KEEP IT IN THE ROAD!

 

  • Beach Area Repairs: Public Works staff have completed repairs to paver surfaces at the Town’s public beach facility. The pavers, which sustained damage during Hurricane Helene, were reset and stabilized to restore safe public access and improve overall appearance.

  • Roadway Maintenance: Public Works staff have stabilized a landslide and completed repairs to curbing and a roadside ditch along Boys Camp Road. These efforts successfully reinforced the damaged portion of the roadway, and additional corrective work is underway to ensure long-term structural integrity

  • Boys Camp Road Permanent Bridge: The Bridge has been designed and the Town has received bids to construct the permanent bridge. The Town has submitted this project for funding through FEMA.  Update 6/23/25: The Town received funding for the damage on the Boys Camp Road Bridge and next steps will be presented to Town Council for consideration once proposals have been assessed. There is no new information at this time.

  • Highway 64/74A Between Lake Lure and Chimney Rock Village: As of 8/20/25, Highway 64/74A between Lake Lure and Chimney Rock Village is only open to locals, which includes residents, property and business owners, and approved construction workers. The checkpoint has been removed but the roadway remains closed to the public at large. For questions, please contact Chimney Rock Village.  Please do not use this road if you do not have to, as contractors have to stop their work to allow for passage when cars go by slowing the recovery process. 

  • NC DOT updates on Highway 64: A temporary road is expected to be open between Chimney Rock and Hendersonville was just extended to June 30, 2027 (YES 2027). For more information, visit NC DOT’s Drive NC link: https://drivenc.gov/?type=incident&id=715074

NCDOT Guidance on Highway 64 - Bat Cave      NCDOT Map of Highway 64 - Bat Cave

  • Update from Gerton Fire and Rescue: "The road closures for Gerton Highway 74 will continue for the next several weeks 9-4. Please plan appropriately as you travel. We would like to also impress that these roads are for local traffic only. We have had a surge in tourists over the last few weeks. Please stay out of the gorge if you do not live there and let them work."

  • Proctor Road: The normal working hours for the project is from 7 AM till 5 PM Monday through Friday.  Proctor Road will be open and passable before 7:30AM, between 12:00-12:30, and after 5:00 PM Monday through Friday, and all day on Saturdays and Sundays. If there is an emergency situation, all equipment will be moved immediately for safe egress/ingress. Update 8/7/25: The timeline for project completion is estimated to be the 2nd week of September (depending on the weather).  

  • Lago Vista Road Extension: Town officials collaborated with Odom Engineering to solicit and review bids for the extension of Lago Vista Road, aimed at improving access to Chimney Rock State Park. The Town is currently working with state agencies to explore partnership opportunities to support the project.

 

LAKE LURE FLOWERING BRIDGE UPDATE

  

Our Hearts are with Lake Lure Flowering Bridge

It is with deep regret that the Town of Lake Lure announces that the Lake Lure Flowering Bridge must be taken down due to the significant structural impacts from last September 2024. The historic structure sustained severe damage during Tropical Storm Helene.  After thorough assessments by two independent engineering firms, it was determined that the bridge is beyond repair and cannot be restored.

Following a competitive bid process, the Town has awarded the contract for removing the bridge to Mitch Contracting.  This process began August 18, 2025.  

For everyone's safety, it is crucial that the public avoid the demolition site at all times.

This includes the area on the east side of the Bridge as well as the area on the West Side, near the Lake Lure Flowering Bridge Education Center. 

Please respect all posted signage and barriers.

The Town of Lake Lure recognizes the historical significance of the Lake Lure Flowering Bridge, and we remain mindful of what it has meant to our community and to the countless visitors who have come to tour it.  We can never thank the Lake Lure Flowering Bridge volunteers enough for their dedication and commitment to beautifying the Bridge and the Town of Lake Lure over the years.  For over a decade, they worked tirelessly to create a gateway to somewhere beautiful!

Thank you for your understanding and continued support during this difficult transition. You may read about the history of the beloved Lake Lure Flowering Bridge here.

 

LAND BASED DEBRIS

 

Personal Property Debris Removal Video

Watch the process in action.

  • Private Property Debris Removal Work Underway in Lake Lure (Zip Code 28746): Private Property Debris Removal (PPDR) operations are now underway in Lake Lure, with crews beginning work over the weekend and steadily ramping up throughout the area.
    • This mission is being led by the U.S. Army Corps of Engineers (USACE) in partnership with TEYA and AshBritt through a mentor-protégé agreement.
    • Approximately 10 to 12 crews are working daily from 7:00 a.m. to 7:30 p.m., with the goal of completing all debris removal, cleanup, and disposal within 30 days.
    • Crews are staging the debris at the space behind the Lake Lure Fire Department and then it will be transported to Enoree, South Carolina.
    • Only properties previously enrolled in the PPDR program are eligible for these services.
    • While this Direct Federal Assistance program is now closed to new applicants, residents may still register for the State’s Mission Assigned Recovery Taskforce (SMART) program.
    • Please note that only improved and maintained areas are eligible for debris removal. FEMA will soon send written notices to property owners whose parcels are not eligible. Residents may be informed in advance that this guidance is forthcoming.
    • Property owners will receive at least 72 hours' notice before any work begins on their property.
    • For questions or concerns, residents are encouraged to contact ppdr@teyacompany.com.

       We appreciate the community’s continued patience and cooperation as we work together to restore and rebuild safely.

  • PPDR in Action: The U.S. Army Corps of Engineers and its contractors are hard at work in western North Carolina, clearing debris left in the wake of Hurricane Helene. USACE, tasked by FEMA, is on the ground supporting Personal Property Debris Removal, clearing fallen trees from private property. Each load removed means safer homes, clearer access, and one more step toward recovery.

Watch the process in action in this video. Each cleared site is a step closer to recovery.

USACE tasked by FEMA are still here clearing debris

DEADLINE EXTENSION!

  • Rutherford County PPDR Deadline Extended to the end of August 2025: Rutherford County Private Property Debris Removal (PPDR) Program: Initially, counties like Rutherford were managing their own debris removal contracts. However, due to widespread cash flow concerns, the State launched the SMART Program to support funding and project management. Under this program, the State now serves as the official applicant for FEMA Public Assistance (PA) reimbursements for PPDR in Rutherford County. Although the State oversees daily operations, it continues to coordinate closely with county officials.

    • Please note that eligibility under the SMART Program follows the same criteria as FEMA’s PA guidelines. As a result, properties that are ineligible for the PPDR through Army Corps will likely also be ineligible for this program.
    • Note that if you applied for debris removal under the PPDR Program in zip code 28746 (at the Arcade Building in Lake Lure) and were approved, you do not need to apply through Rutherford County. If you missed the opportunity to apply for debris removal in zip code 28746, you may apply through Rutherford County.  If you have questions about the program, please call (828) 319-2880 or email ppdr@debristech.com.

NC - Rutherford County - PPDR flyer

  • Rutherford County Debris Removal/Drop Off//Free Mulch: Rutherford County has also been removing debris from the roadways. Rutherford County is giving away free double-ground mulch-like product. The mulch is available at the Rutherford County Landfill, 656 Laurel Hill Drive, Rutherfordton, NC. The Rutherford County Landfill is located at the end of Laurel Hill Drive, which is only accessible via Industrial Drive off of Hwy 221 South. Phone: 828-287-6125. Hours for pickup are Monday-Friday 10:00 am-2:00 pm. Hours for drop off: Saturday 8 AM–4 PM, Sunday-Closed, Monday-Friday 8 AM–4:30 PM.    

  • Polk County Transfer Station/Landfill:  Address: 322 Landfill Rd, Mill Spring, NC 28756, Phone: (828) 894-3737, Hours: Saturday8 AM–4 PM, Sunday-Closed, Monday-Friday 8 AM–4:30 PM. 

 

PRIVATE WELLS

 

If you have a private well and lowering the lake has affected your well, then lake water may have been infiltrating your aquifer.

Well graphic

  • The first signs are sedimentation in your water, then air introduction to your system. 
  • The Town anticipates the lake will continue to be lowered for several more weeks. 
  • We do not currently have a date for refilling the lake as it is dependent upon the silt/sedimentation/debris removal being overseen by the USACE.  
  • It is recommended that individuals experiencing these indicators consult a well company.
  • Sedimentation can be filtered, but air usually means you need to dig a deeper well to retrieve water from a protected aquifer below the clay or rock layer.

The Town of Lake Lure consulted with the North Carolina Department of Environmental Quality regarding this matter to see if they could be of any assistance.  They provided the following link for individuals seeking financial assistance with their wells: Water Well Trust.  You may learn more about applying for this assistance here.

Well Water Trust

Additionally, here are resources for assistance with testing and disinfecting personal wells.

1)  Foothills Health District: Please click on the following link for Emergency Drinking Water Well Disinfection Procedures

     http://www.foothillshd.org/images/forms/4000/4001/FoothillsHealth_WellWaterDisinfection.pdf

2)  Broad River Water Authority: 828-286-0640

     https://www.ncbrwa.com/ 

3)  James & James Environmental Management, Inc.: 828-697-0063 

     https://www.facebook.com/jamesandjames1992/Roadways: The Town of Lake Lure is grateful for the support of the community as so many trucks (over 300 per day) are up and down the roadways hauling off silt and debris.  This phase of the recovery remains challenging, but the restoration that is being done is nothing short of amazing.  Once the debris is finally cleared, the roadways will be assessed and the Town will work to restore roadways that have been impacted by the traffic from heavy trucks. Public Works crews are working on Town roads and mudslides every week. We are grateful to the NC Department of Transportation for their work to patch areas of Highway 9 and Highway 108 into Lake Lure, to make the roadway safe. 

 

GUIDANCE ON LAKEFRONT DEBRIS AND DEBRIS UNDER LAKE STRUCTURES

 

If you are a lakefront property owner, this photo illustrates a situation you might face with your lakeside debris. As you can see from the photo, the debris that has been collected near the dock is too far away from the excavator to remove it at the current lake level.  The US Army Corps of Engineers contractors have confirmed that they plan on removing debris in this general location when the water comes back up. In other words, they will be making another round to pick up debris once the water level is raised in the coming weeks. We do not have a date for raising the lake levels at this time, but this information will be posted on the town website when we have a timeline.

Barge Removing Debris and Silt

 

CONTRACTOR INFORMATION

 

Only approved contractors may go on the lake at this time, but sea wall restoration is now possible with the proper permitting.  Building contractors should submit a scope of work regarding lake use activities (with permits) to Community Development.

If work is to be done from a boat, a 2025 Service permit sticker will also be required. Please contact the Parks, Recreation, and Lake Office to purchase the service permit sticker.  You may emailkmartin@townoflakelure.com"> kmartin@townoflakelure.com with any questions.

Click here for additional information on contractors.

 

DAMAGED LAKE STRUCTURES

 

The Community Development Department has created a map showing most of the seriously damaged lake structures, over 100 boathouses.  These are properties that the owners agree to the demo of the boathouse. If you have damages, be aware that you will need to contact the Community Development Department about permitting for repairs or replacement.  Permits are being issued and work is being done on lake structures now, but all work must be authorized. 

  • For property owners who signed up for the no-cost demolitions by the Army Corp, they are working on their plan now and we will notify you as we have more specific timing information. 
  • We have confirmed that, if you are signed up for the condemnation/removal program, they will be contacting you individually for a “right of entry” agreement prior to beginning the work.
  • We anticipate these demolitions within the coming weeks. 
  • Please contact Community Development Staff for more information about the Army Corp program, as well as your permitting, at kmartin@townoflakelure.com or 828-625-9983, x 135.

 

CELL TOWER

 

The cell tower site is off Boys Camp Road in the old campground. The location shifted 100 feet back to accommodate the change in the topography due to the storm. It will still be 125 feet from property lines and will be fenced in. The tower will be 195 feet tall and will be a sleek design. Construction for the tower is expected to begin this summer 2025.  

The Cell Tower is on track for August construction.  Due to the Helene damage delay, the tower applicants had to go back through the state and federal permitting process again.  The NC State Historical Preservation Office provided a quick approval and we are all looking forward to improved cell signals and 5G service! The tower applicants are still on track and confident of breaking ground in late July.  They were doing some preliminary sample drilling on the site this month!

Update 8/13/25: The project is moving forward. Tillman Construction owns the tower and AT&T is the primary vendor though there will be room for additional vendors. A custom mounting is being designed to elevate the equipment, including the generator.  Construction is slated to begin 8/21/25.

 

BEYOND FEMA – SUPPORT FOR HURRICANE HELENE SURVIVORS

 

Hickory Nut Gorge Outreach - Local Food Pantry: (828) 625-4683 Monday, Thursday, 10:00 AM – 4:00 PM and Fridays 10:00 AM - 1:00 PM  https://hickorynutgorgeoutreach.org/

Legal Aid NC Helpline: If you wish to contact Legal Aid NC for disaster-related legal issues, call our Helpline: Toll-Free: 1 (866) 219-LANC (5262) 8:30 AM – 4:00 PM, Monday – Friday. Legal Aid of North Carolina is not your typical law firm—they are the nonprofit law firm for the state. They are dedicated to delivering justice and ensuring that everyone, regardless of their circumstances, has access to legal help and support when it matters most. https://legalaidnc.org/what-we-do/

NC Department of Insurance (DOI) is coordinating with law enforcement agencies, emergency management, fire departments, rescue squads, charities, churches and civic groups to do everything we can at the state and local level to assist the victims. DOI Consumer Assistance will be on the ground to help with insurance claims and other needs. The following web page is updated with the latest information on the DOI Hurricane Helene recovery efforts. https://www.ncdoi.gov/hurricane-helene-response-and-recovery

RHI Legacy Foundation: RHI Legacy is committed to impacting health and wellness in Rutherford County by making grants to support organizations and initiatives aligned with the Foundation’s grant focus areas: Chronic disease, Healthy Eating, Active Living. www.rhilegacyfoundation.com

United Way: https://www.unitedwaync.org/

United Way of Rutherford County: www.unitedwayofrutherford.org

The Community Foundation for Western NC (CFWNC) Hurricane Helene Relief and Recovery Effort: (Regional Funders, Donors and Others Coordinating for Hurricane Relief in Western North Carolina). CFWNC activated its Emergency and Disaster Response Fund to accept and disburse funds supporting a regional response and relief efforts in 18 counties of Western North Carolina including the Qualla Boundary on September 29. Funds ensure that nonprofits have the resources they needed for the critical early response and continuing recovery. Administrative fees are waived so that every dollar goes directly to assistance.  *To donate by check: make your check payable to The Community Foundation and mail it to 4 Vanderbilt Park Drive, Ste. 300, Asheville, NC 28803; please include EDRF in the memo line. $17,498,653 in 394 Grants Awarded as of 1/1/25. To apply for a grant visit:  https://cfwnc.org/initiatives/hurricane-helene-relief-and-recovery

North Carolina Community Foundation: Bringing together generous people and connect them to causes and organizations they care about. Mission: to inspire North Carolinians to make lasting and meaningful contributions to their communities. The North Carolina Community Foundation’s Disaster Relief Fund aims to provide assistance in the months and years ahead. “Our Disaster Relief Fund is going to be providing help with long-term recovery and unmet needs. It will complement the work already underway in western North Carolina with grants going out to organizations in early 2025,” said NCCF President and CEO Jennifer Tolle Whiteside.  More than $10 million has been raised so far for the Disaster Relief Fund, including a $7.5 million gift from Lilly Endowment Inc. Visit the following link to apply for a grant: https://www.nccommunityfoundation.org/

 

FUNDING OPPORTUNITIES FOR BUSINESSES

 

The Community Foundation of Western North Carolina Grants Directory: https://cfwnc.org/grantseekers/grants-directory 

The Community Foundation is a nonprofit organization established in 1978 to build a permanent pool of charitable capital for the 18 counties of Western North Carolina including the Qualla Boundary. We work with individuals, families and corporations to create and manage charitable funds and make grants to nonprofits or public agencies in our region. 

In partnership with fundholders, the Foundation has awarded more than $387 million in scholarships to students and grants to nonprofit organizations and public institutions across our 18-county region and beyond. We manage $462 million (March 2025) in assets with a long-term investment strategy that permanently protects and grows these funds.

A COMMITMENT TO THE REGION

Mission: The Community Foundation of Western North Carolina inspires philanthropy and mobilizes resources to enrich lives and communities throughout the region.

Vision: Our vision is a vibrant and equitable Western North Carolina where all people can find opportunity and enjoy the region's many resources.

Western NC Strong Recovery Loans: https://www.mountainbizworks.org/get-funding/

Where traditional banks see risk, we see massive opportunities. For over 30 years, Mountain BizWorks has been saying yes to entrepreneurs, whose financing needs have often been overlooked and underfunded. Supporting Western North Carolina’s small businesses get the capital they need to start, grow, and thrive is our passion.  What they provide: Mountain BizWorks believes in the power of local entrepreneurs to create a vibrant local economy. While traditional banks often see start-up and early-stage businesses as too risky, we see them as Western North Carolina’s future.  Mountain BizWorks specializes in providing financing to help Western North Carolina small businesses launch and expand, by offering non-traditional loans from $1,000 to $500,000. Because all loan decisions are made locally, we are able to support your capital needs and requests with expediency.

 

FINANCIAL SUPPORT/APPLICATIONS

 

The following chart illustrates the financial support the Town of Lake Lure is currently seeking, in addition to Federal and State Funding requests that have been made on behalf of the Town through our political representatives (disaster management planning experts) and Hager Strategic Solutions (lobbyist).  They are assisting the Town with post-disaster federal funding applications and requests to expedite our recovery process.

There are now 34 projects that have been submitted to FEMA for consideration of funding and the Town is awaiting their review and feedback.

8/13/25 update: Nine FEMA-funded projects have been obligated. The Town has received $2,325,171.92 for seven of these, and two additional reimbursements totaling $38,212.80 are pending. Delays persist for projects over $100,000, and staff have begun contacting elected officials to address these concerns. 

8/20/25 update: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.

Several other projects are currently under review by FEMA. While the process continues to move slowly, we are seeing progress, and these projects are inching closer to obligation.

  • Diving Operations at the Dam ($700K range)
  • Flowering Bridge Demo: Version 0 - will have to argue costs. 
  • Community Center/Welcome Center: Came back at $160,000, which is far too low.
  • Marina Docks
  • Lake buoys and booms.

Organization

Funding Request

Status

State of NC-DEQ-Water

(Loan with potential forgiveness)

$3,000,000

Application under review

FEMA-Revenue Replacement

(Loan with potential forgiveness)

Up to $5,000,000

Financial data under review; additional data being provided

FEMA reimbursements

Up to $7,500,000

5/2/25 Update: 5 projects now obligated for a total of $3,224,564.61.

·$862,186.69 Received 4/25 for a Category A (Debris Removal)

5/18/25 Update: $754,185.81 (anticipated 5/25) for a Category B (Emergency Protective Measures) (payment received)

5/23/25 Update: Received a check for $65,390.00 for Category A Town Wide Vegetative Debris Removal from ROW and Public Property.

A new project was obligated for $118,323.67 for Category B Temporary Hydroelectric Plant Emergency Repairs. (payment received)

6/23/25 Update: Received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C); 

8/4/25 Update: Received $8,250 for Temporary Town Hall Facility (Category B);  Received $13,255.75 for Lake Lure Dumpster Rentals (Category A);

DEQ-ARPA Reimbursement (non-storm related)

Up to $3,000,00

Submission under review

Private Donations

Up to $90,000

Deposited; being held for future disbursement under discretion of Town Council

Other Revenues and Payments from Insurance proceeds and claims

Up to $5,000,000

50% has been approved for release

1/7/25 Update: 50% received.

1/31/25 Update: $1.3 million insurance payment for damage to Town Hall. 

NC Treasurer Cash Flow Loan

$3,423,122.89

3/21/25 Update: Received   

6/23/25: The Town was offered an additional $2.8 million in cash flow funds from the State Treasurer.  A recommendation regarding this offer will be made to Town Council for consideration.

6/25/25: Town Council approved the loan.

7/29/25: Received a $2.8 million dollar loan disbursement this week from the NC Treasurer

 

MONETARY DONATIONS

 

Our community, along with many of our neighbors, has been devastated by the catastrophic flooding caused by Hurricane Helene. The Town of Lake Lure, NC is deeply grateful for the support our community has received.  We have had numerous requests to establish a mechanism for financial donations. Please click on the following link to donate to the Town of Lake Lure Storm Recovery Fund.  

https://www.paypal.com/ncp/payment/WXB6HYYE8Y5PJ

Additional options for monetary donations include the following: 

 

STORM RECOVERY ACCOMPLISHMENTS

 

Swift evacuation by first responders saving countless lives 9/27/24.

Countless rescues first responders during and following Hurricane Helene.

Coordination with the Rutherford County Emergency Management during and throughout the storm.

Dam assessment and stabilization immediately following the storm event 9/27/24-9/29/24.

Communication with the Rutherford County EOC and FEMA for recovery immediately following the storm.

Coordination with volunteer groups to provide hot meals, shower services, restrooms, and handwashing stations in strategic locations by 10/1/24. Christian Aid Ministries served 8,080 hot meals and assisted 43 homeowners with clean-up of their homes and property.  There were 164 volunteers and they spent 2,457 hours assisting our community!

Creation of donation stations to disseminate supplies throughout town by 10/1/24. 

Cleared Highways and Town roads within days of the storm.

Restoration of water service throughout Town with water quality testing allowing Boil Advisory lifted 10/14/24 and 10/16/24 respectively.

Rapid repair of power services throughout Town by Duke Power and REMC.  

Establishment of temporary communications systems through Starlink (10 systems) and Cell on Wheels with AT&T and Verizon 10/16/24.

Replacement of fiber to re-establish internet and cell service to the area 10/18/24. 

Repair to the left abutment of the Dam by 10/27/24 with 2,494.64 tons of material securing the area.

Army Corps of Engineers contract signed with AshBritt to oversee lake debris and silt/sedimentation removal during a 160 day period of performance beginning 10/28/24.  Debris removal began 11/4/24.

Emergency repairs to the sewer system completed, allowing "no flush order" to be lifted for most on 10/28/24.

Reopening of the Dam Bridge on Buffalo Shoals Road on 10/31/24.

Dittmer Watts Nature Trails and a portion of the Green Space reopened on 11/19/24.

Pressure Reducing Valve Construction in Lake Lure Town Center successfully completed 11/22/24.

The Boys Camp Road Temporary Bridge was completed 11/26/24.

As of 1/23/24, Over 32,782 CY of debris were removed from the right of way, 27,669 tons of sediment and silt have been removed from Town and the Parks, 24,558 cubic yards (CY) of debris have been removed from the Lake.

1/10/25: Burnt Ridge Landslide repair completed.

1/7/25: 50% of insurance payments received.

1/22/25: Contracted with lobbyist Hager Strategic Solutions (lobbyist). 

1/22/25: Proclamation to open Chimney Rock State Park as soon as possible to bring in tourism to the area and strengthen the economy.

1/31/25: Culvert repair on Hummingbird Cove completed.

1/31/25: $1.3 million insurance payment received for damage to Town Hall. 

2/11/25: Waste Water Treatment Plant is now operational.  Repaired 3 water leaks throughout the water system

2/14/25: Storm drain box culvert repaired at corner of Memorial Hwy and Charlotte Dr

2/19/25: Youngs Mountain Trail landslide repaired

2/21/25: Green Space drainage repairs completed, grass replanted, and dry creek beds put into place.

2/28/25: The Town of Lake Lure and all those in areas code 28746 are eligible to apply for a free option for debris removal program through the USACE.

3/7/25: Debris removed from Morse Park trails and grass replanted in that area.

3/14/25: FEMA approval of the mission assignment for Lake Surface Debris, silt, and sedimentation removal through FEMA and the US Army Corps of Engineers.

3/18/25: Community Forum held with FEMA, USACE at The Lakeside Terrace with approximately 200 attendees.

3/18/25: United Way presented Fire Chief Dustin Waycaster a check for $50,000 for a new heart monitor for Firefights/AMTs.

3/27/25: Reservoir Drain Valve Installation complete.

4/24/25: 371 +/- boats that have been removed from the lake.

4/25/25: Reopened the East entrance to Morse Park.

5/2/25: $862,186.69 Received 4/25 for a Category A (Debris Removal)

5/11/25: $754,185.81 Received for a Category B (Emergency Protective Measures)

6/12/25: New seawall completed at the Lake Lure Gazebo

6/13/25: New pavers replaced broken and missing pavers in the Morse Park walkway and in front of the Lake Lure Beach. 

6/17/25: The Lake Lure Beach was replenished with fresh sand.  

6/23/25:  The Town received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C)

6/25/25: Cash flow loan approved for $$2.8 million.

6/27/25: Downslide repaired on Angler's Way. 

7/21/25: Repairs on Boys Camp Road completed.

7/21/25: Debris and silt/sedimentation removal from the Rumbling Bald Beach and Marina are complete.

7/28/25: Town Hall relocated to temporary office space in The Landings. The official opening date for the public is 8/1/25.

7/28/25: The Town received the $2.8 million loan disbursement this week from the NC Treasurer.

8/7/25:  Received $8,250 from FEMA for Temporary Town Hall Facility (Category B);  Received $13,255.75 from FEMA for Lake Lure Dumpster Rentals (Category A).

8/13/25: Silt/sedimentation removal began in Washburn Marina and coves around the lake, like Tryon Bay.

8/20/25: Asheville Tennis Association presented the Town of Lake Lure with a check for $19,000 to help rebuild our future tennis/pickleball courts.

8/20/25: The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.

ONGOING

  • Emergency repairs to the sewer system.
  • Constant removal of silt, sedimentation, and debris from the lake and roadways.
  • Removal of condemned boathouses and personal property debris removal.
  • Town officials are working to develop a comprehensive plan for future prosperity in the Town of Lake Lure.   

 

WHAT’S OPEN IN THE TOWN OF LAKE LURE!

 

Welcome to Lake Lure

Lake Lure Welcomes Visitors Back As Recovery Continues: While visitors should be mindful of ongoing recovery efforts, several local businesses and recreation areas have reopened.  There are a number of attractions that are open in the area. Lake Lure hotels, lodges, bed & breakfasts, and our amazing restaurants are open for business!  Our local businesses greatly appreciate your patronage!  Please visit the area and encourage others to visit as well. 

Download the 2025 Travel Guide here.  

Please visit the Local Restaurant Guide

And here are some of the amenities that are currently open to the public.  

  • Morse Park Walkway and the Lake Lure Gazebo
  • Dittmer-Watts Nature Trails
  • Lake Lure Green Space
  • Pool Creek Picnic Park
  • Youngs Mountain
  • Rumbling Bald Golf Courses
  • Chimney Rock State Park – Rumbling Bald Access
  • Chimney Rock State Park – Now open daily by reservation - Click here to reserve your tickets!

Additionally, horseback riding is available in the area along with zip lining, escape rooms, a candy cabin, and so much more!

New Playground Planned: The Town has been approved for a grant for a replacement playground, which will be placed in Morse Park in October, just inside the walkway to the Gazebo.  Please join us!  A Design Day will be held to get input from local children and adults on 7/30/25.    Click here for more information.

Buffalo Creek Park/Weed Patch Mountain Trail/Upper Boulders Trail: Ongoing work is also taking place at Buffalo Creek Park, Weed Patch Mountain, and the Upper Boulder Trails by the National Guard, Carolina Climbers Coalition, Rutherford Outdoor Coalition, EcoForesters, and AmeriCorps. We cannot thank them enough for their time and support!  Update 6/17/25: Progress continues to be made on Upper Boulders Trail, and a small section may be opening soon. The Town will receive a grant of $50,000 to assist with restoration.  Please stay tuned for updates!

Upcoming Events:

  • 9/27/25: The Town of Lake Lure is planning a special ceremony commemorating Hurricane Helene at 11:00 at the Morse Park Gazebo.  The event will honor those who lost so much during the flood while recognizing the resiliency of the Lake Lure Community and the tremendous recovery that has taken place.   

  • 10/5-11/25: Cycle NC  Mountain is Coast ride, starting In Lake Lure

  • 10/10/25: Reopening Celebration and Ribbon Cutting for Buffalo Creek Park

  • 10-13-15: KaBOOM Playground Building Project in Morse Park

  • 10/18-19/25: Hickory Nut Gorge Outreach Fall Arts and Crafts Festival

  • 10/18/25: Lake Lure Artist's Show and Sale

TEMPORARY TOWN HALL

 

The Landings is the new temporary office space for Town Hall and the Police Department.

  • The Town Council approved a month-to-month lease agreement with The Landings to support continued operations while the Town and FEMA work together to identify a permanent solution for the damaged municipal facilities.
  • Starting in August, all Town Council and advisory board meetings—with the exception of the Lake Advisory Board (LAB) and the Parks and Recreation Board—will also be held at this new location.
  • LAB and Parks and Recreation Board meetings will continue to be held at the Parks, Recreation, and Lake Offices.
  • Lake Lure's Town Hall building at 2948 was flooded during Hurricane Helene.  The status of the building itself is uncertain at this time, as the Town is awaiting FEMA's determination on the facility and any funding.

 

COMPREHENSIVE PLAN

 

The Town has officially initiated the Comprehensive Plan process. To help guide this important effort, an 11-member steering committee has been established. In addition to advising on the overall process, committee members will help promote community engagement, review draft materials, and serve as a vital connection between the public, planning staff, and Town leadership.

  • The steering committee will begin meeting prior to the public input phase.
  • These early meetings will help establish the framework and key themes to ensure that public engagement is inclusive, focused, and productive.
  • The public will have multiple opportunities to participate in shaping the plan, including through surveys, community input sessions, and town hall meetings—anticipated to begin in October.

 

QUESTIONS/SUGGESTIONS

You may review previous Storm Recovery Updates in Town News at www.townoflakelure.com

For questions or suggestions, please email Communications@townoflakelure.com