Lake Lure Storm Recovery Updates and More - 10/16/25
As the essential lake restoration project nears completion, the Town of Lake Lure remains committed to working with federal leaders to ensure this effort is successful. Currently, the Town has not received any official confirmation from FEMA or US Army Corps of Engineers (USACE) on the final date for completion of the project. As we reported last week, the Town has learned that the temporary slowdown in operations has occured while FEMA and USACE evaluate the costs and remaining scope of work necessary to complete the project.
Town officials are also actively communicating with state and federal representatives to ensure that FEMA and USACE remain involved in the completion of this critical work. These representatives are fervently advocating on the Town’s behalf to secure continued federal partnership and support for ongoing work to fully restore Lake Lure. The Town will post an update as soon as any additional information becomes available.
It is important to emphasis that the improvements that have been made to date are nothing short of remarkable. The work that has been done is so much more than the Town could have ever managed to do without the support of FEMA, the USACE, and all the many contractors who have helped with this effort. The Town of Lake Lure is forever grateful!
HOW MUCH SILT AND DEBRIS HAVE BEEN REMOVED FROM LAKE LURE?
The US Army Corps of Engineers (USACE) and their contractors have provided the following data on silt and debris removal from Lake Lure as of 10/12/25.
-
A total of 1,254,230 tons of sand/silt and sediment have been removed from Lake Lure. That's 56,139 tons additional since our last report of 10/2/25!
- A total of 100,374 cubic yards of debris has been removed from the waterway. That's an additional 189 cubic yards since the last report.
Lake Lure Debris Removal at Marina Cove October 142025
WHAT IS THE LAKE LEVEL
The Lake Level is currently at about 968 Mean Sea Level (MSL).
- Full pond in Lake Lure is 990.5 MSL.
- The current plan is to let the lake naturally rise to approximately 970 MSL.
- The speed at which the lake will refill to this level is dependent upon the weather.
- The plan is to maintain the lake level at about 970 MSL for the remaining lake restoration work that will be done.
- Any changes in lake levels beyond this point will be posted in Town News at www.townoflakelure.com.
HOW LONG WILL THE LAKE BE DOWN?
We are unable to specify the length of the drawdown period as this is dependent upon the sedimentation and debris removal process being overseen by the USACE.
- When a change in the lake level is planned, it will be posted here.
- As you can see from this photo above, work in the Washburn Marina area is going strong.
- Throughout the lake drawdown, Town engineers and staff will be scheduling work and inspections on the dam and the sewer system.
CAN WE ACCESS THE LAKE?
The Town of Lake Lure and all businesses are open and welcoming visitors; however, the lake itself remains closed to all unauthorized personnel.
- Lake Lure is currently a Federal Work Site.
- Do not enter the lake or the lakebed for everyone's safety, and to avoid fines.
WHERE DOES ALL THE SILT/DEBRIS GO?
The sand and the construction and demolition material are taken to the Republic Landfill in Union County, SC, out of an abundance of precaution.
- The vegetative material is taken to the area behind the Lake Lure Fire Department, where it is reduced.
- The mulch is hauled to a landfill in Canton, NC.
WHEN WILL THE LAKE REOPEN?
Lake Lure Debris Removal by USACE September 2025
The lake restoration is a dynamic process so the date for reopening the lake is uncertain.
- We do not have a definitive timeline for completion at this time.
- The USACE originally thought they may complete their work by the end of October; however, this date may go further into the fall season.
- We are grateful for every day they remain working in Lake Lure!
- The Town of Lake Lure remains hopeful that we will be able to reopen the lake in the late spring of 2026.
- You may read the Town's Press Release on the reopening timeline here.
LAKE LURE WATER QUALITY
We are pleased to report that the latest results (September 2025) are all within acceptable limits.
- You may review the updated spreadsheet, which illustrates all the water sample data received by the Town of Lake Lure.
- For questions, please contact Communications@townoflakelure.com.
BEYOND THE LAKE, HOW WAS THE TOWN IMPACTED BY HURRICANE HELENE?
The impact to the Town of Lake Lure is unimaginable.
-
Unfortunately, Lake Lure’s nearly 100-year-old utilities infrastructure (sanitary sewer systems and wastewater treatment plant), our dam, Town Hall, Welcome Center, and municipal buildings, the Washburn Marina and floating boardwalk, the lake itself, and surrounding roadways and vehicular bridges were also significantly damaged by the devastating hurricane and flooding.
-
Town officials have been working with FEMA, applying for grants, working with local and state representatives to obtain funding, and utilizing existing capital from the small Town's budget to restore these vital resources. The Town cannot take action to restore or rebuild these buildings until FEMA makes the final determination and funding becomes available to address these facilities.
-
Updates will be provided in these updates as new information becomes available on any of these Town facilities and utilities.
CELL TOWER UPDATES
For those who have experienced challenges with phone service in Lake Lure, you can see the progress on the cell tower here!
- The location of the cell tower is off Boys Camp Road on the old campground property.
- The site and access road grading began 9/2/25.
- Tillman Infrastructure is building the tower and will own it.
- They will lease antenna space to cellular service providers and AT&T will be the primary provider.
- Verizon has leased the next highest space and T-Mobile will be the third provider.
- The antenna is expected to be in place this winter.
IN THE NEWS
1. Lake Lure Arts and Crafts Festival happening this weekend, By Morgan Starling The Daily Courier
The popular Lake Lure Arts and Crafts Festival is back on Saturday and Sunday, with more than 80 vendors planned to participate.
The festival, which will be located adjacent to the Lake Lure Inn, is scheduled for Saturday from 10 a.m. to 5 p.m. and Sunday from 10 a.m. to 4 p.m.
“After the trials of Hurricane Helene, Lake Lure is not just rebuilding, we are emerging stronger,” said Lake Lure Mayor Carol Pritchett. “This year’s Arts and Crafts Festival marks more than a celebration of art. It is a tribute to our resilience, our neighbors and our shared future.”
More than 80 vendors will be on site, offering everything from food to books, pottery, leatherwork, soaps, jewelry and more. Some of Chimney Rock Village’s businesses will also have booths set up.
Also, from 9 a.m. to 3 p.m. Saturday will be the Lake Lure Artists Show and Sale, located at the Lake Lure Beach Pavilion.
There will be paintings, pottery, fiber arts, stained glass, gourd art, jewelry and other items for sale, and multiple raffle drawings for artwork will also take place throughout the event.
The Lake Lure Arts and Crafts Festival raises funds to support Hickory Nut Gorge Outreach, a 501c3 nonprofit that serves families in the Hickory Nut Gorge community, which extends into four counties.
The organization’s mission is to help eliminate hunger and provide emergency services to those in need, doing all work with love and compassion.
“I invite everyone to come, explore and enjoy the town of Lake Lure and support our local food pantry,” Pritchett said. “Your presence renews hope, supports our local vendors and businesses, and helps us show the world that Lake Lure’s spirit endures.”
To get to the festival from Hendersonville or Asheville, festivalgoers are told to take I-26 to exit 67, turn left on N.C. 109 to Mill Spring, then turn left on N.C. 9 to Lake Lure.
Roads are still closed from the Bat Cave side.
The Lake Lure Arts and Crafts Festival is put on by the Lake Lure Arts and Crafts Festival Coordinating Committee.
2. North Carolina Gov. Josh Stein announces new preventative flood initiative following Hurricane Helene
North Carolina Governor Josh Stein announced on Thursday, $6 million in grants to protect against flooding in North Carolina following Hurricane Helene. Watch Newscast here
North Carolina Governor Josh Stein announced on Thursday, $6 million in grants to protect against flooding in North Carolina following Hurricane Helene. The grants are part of the Flood Resiliency Blueprint Program. The program is a data-driven initiative that helps local governments develop strategies to protect against flooding.
"A year ago, Helene's record rains overwhelmed the French Broad, causing the river to crest at nearly 25 ft," Stein said. "Investing in resilience and enhancing the French Broad River Basin will help us better protect towns like Marshall from future flooding and protect rivers from pollution.”
3. Lake Lure continues refill as restoration work advances after Helene Town officials say the lake has reached 968 feet and will rise gradually to support ongoing recovery projects. By Dee Pridgen October 14, 2025 10:09 am
LAKE LURE, N.C. (828newsNOW) — The town of Lake Lure says its namesake lake continues to slowly refill following months of restoration work tied to recovery from Tropical Storm Helene.
Town officials reported Monday that the lake level has reached about 968 feet above mean sea level, with a goal of allowing it to naturally rise to roughly 970 feet in the coming weeks. A full pond level for Lake Lure is 990.5 feet, according to the town.
The speed of refilling will depend on weather conditions, and officials plan to hold the lake at around 970 feet to accommodate ongoing infrastructure and restoration projects.
Lake Lure was significantly impacted by flooding and sedimentation after Tropical Storm Helene swept through western North Carolina in September 2024, damaging roads, utility systems, and the dam area. Restoration work began earlier this year as part of a long-term recovery plan.
Updates on lake levels and project progress will continue to be posted on the town’s website. Residents can also find updates and detailed information about the long-term recovery plan in the “Lake Restoration Update.”
4. Recovery abundant after Helene, say western North Carolina leaders. By Bill Horner III, 10/15/2025
Recovery and resilience were prevalent themes at Business North Carolina’s Rural Economic Summit in Hickory Tuesday and Wednesday, where speakers highlighted the economic realities of a post-Helene western North Carolina.
That recovery has been abundant but slow.
“We’ve made progress, but we have a long way to go,” says keynote speaker Patrick Woodie, the president and CEO of the N.C. Rural Center.
Plenty of bright spots were highlighted. Kit Cramer, the CEO of the Asheville Chamber of Commerce, said the city was without running water for 53 days. The day after the storm, though, power was restored to the chamber’s offices. No running water, but Cramer said because the internet was working, they opened as an emergency operations hub. Employees who were able to get fuel for their automobiles were eager to work. Portable toilets and an abundance of power outlets allowed Cramer and her staff to focus on raising funds, communicating needs and advocating where they could.
That included working to help some of the 20,000 farms damaged by the storm — leading her office to bring in animal feed and distribute other supplies to farmers and others in need.
Tom Dempsey, the founder of SylvanSport in Brevard, said his company didn’t lose power, either. But because so many of his employees did, “our building became a gathering point. Even though so many of them had damage at their homes, they wanted to come back to work,” he said.
Over in Boone, David Jackson said seeing water flow under the iconic Doc Watson statue downtown was a stark visual early during flooding. But Jackson, the CEO of Boone’s Chamber of Commerce, said downtown Boone “was one of the least devastated areas.”
“You saw water where you’ve never seen it before,” he said.
Needs changed by the hour. When waters receded and the region’s workforce began to return, the collective focus was on recovery efforts — and businesses allowing staff to join recovery efforts proved an “incredibly valuable” resource.
About 10 days after the storm, though, Jackson said he and his team were temporarily forced to shift efforts: they found themselves spending more time debunking false narratives — largely critical of FEMA’s response, spread primarily on social media — than actual recovery work. It was a political narrative spun mostly by people not in the area and “did awful damage” to the recovery effort.
In Asheville, Cramer said she was delighted to see locals “piling on” in response to false posts. She and others praised FEMA’s work and noted an agency program, Surge Capacity Force, that allowed FEMA and other federal employees to work in recovery efforts as volunteers. She knew of five who made the trip to provide assistance in the Asheville area, including one from Alaska.
As a mother, she likened the region’s Helene experience to childbirth: you’ll never forget the pain, but the memories of that subsides six, seven and eight years later, as the child grows. Western North Carolina, Cramer said, will emerge from the Helene experience “better and stronger.”
Still, business recovery has been unsteady, particularly since Helene wiped the month of October off the revenue calendar, as well as the foliage season — keys to the economic engine driving so much potential. With visitation still down, many businesses are still in dire straits.
“An ill-timed weekend rain could mean the end of some businesses,” Jackson said. “Covid loans aren’t enough, so we continue to beat the drum for western North Carolina.”
Recovering businesses, he said, aren’t looking for a handout, but rather a little grace — and for visitors to come and spend a little money there.
Wit Tuttell of VisitNC said his office still has to fight with the perception of some potential visitors that North Carolina isn’t open for business. In surveys his office conducted, 68% of respondents thought the state’s coast had been severely damaged by Helene; another 78% thought the Piedmont region was adversely affected.
“The brand of the state has been hurt,” he said.
North Carolina has the fifth-most tourism in the country, and in a typical year, only two or three counties will see drops in tourism spending. This year, that number is 31. In Avery County, Grandfather Mountain CEO Jessie Pope said the nonprofit foundation operating the attraction suffered $3.1 million in lost revenue from Helene.
Typically, about 40% to 50% of natural disaster damage is covered through federal program funding. Matt Calabria, the director of the Governor’s Office for Western N.C., said only about 12% of Helene’s $60 billion price tag has been covered so far.
The state, of course, continues to seek additional federal funding, but some damage doesn’t have a clear financial cost. In a session on healthcare workforce challenges, Susan Mims, the CEO of Dogwood Health Trust, emphasized the need for more behavioral health services in the wake of Helene. Services were already limited even before the storm, she said, and after the heroics of that first year of recovery, needs typically spike significantly the following year.
“This will be a challenge for all of us,” she said.
Jackson, of the Boone Chamber, said looking back, 12 months later, “We’re not calling it an anniversary.”
“It’s a year of commemoration,” he said. “We’re ready to take steps toward progress.” Read more here.
5. Hurricane Helene Washed Away a Rainbow Bridge. Then the Collars—and Hope—Began to Resurface: As the town of Lake Lure rebuilds, the tribute to lost pets remains a beacon, By Lindsey Liles, Garden & Gun. October 10, 2025
When Hurricane Helene devastated Western North Carolina, the Flowering Bridge of Lake Lure was one of many structures swept away in the waters—and with it,...Read more here
6. Hurricane Helene: One year after the storm that changed lives. October 9, 2025 10:00 am by Quill Sanders, The Western Carolinian.
Hurricane Helene devastated WNC on Sept. 27, 2024. Now, one year after the storm, communities across the region gather to remember all that was lost and celebrate everyone who helped bring normalcy back to the mountains and the resilience of WNC.
WCU held a remembrance ceremony for Hurricane Helene on Friday, Sept. 26. Haywood County held a ceremony on Saturday, Sept. 27.
At WCU, The Center for Community Engagement & Service Learning and the Mountain Heritage Center co-hosted the campus Day of Observance. There was a bell ringing for community members and college students to commemorate their experiences with the hurricane. There was also a listening booth in the Catafount sharing oral histories of everyone who helped in the aftermath of Helene.
“We were trying to think of ways that people could opt into being reflective about Helene, we felt like it was too soon to do anything really big,” said Heidi Buchanan, the associate dean of the Hunter Library. “This was our way of honoring the one-year anniversary; acknowledging that it still feels like yesterday to people.”
The Remembering Helene listening booth featured stories from WCU’s Oral History collection and “Come Hell or High Water,” a project by Buncombe County Special Collections. Read more here.
KEEP IT IN THE ROAD!
Memorial Highway (64/74) between Lake Lure and Chimney Rock is open. NC Department of Transportation (NCDOT) has been repaving portions of 64/74 in Lake Lure and the new roadways are greatly appreciated!
You will also see that optic fiber is being installed underground along 64/74 so anticipate delays.
Highway 64/74A Beyond Chimney Rock Village: Highway 64/74A heading West beyond Chimney Rock Village remains closed to the public at large. It is open to "locals", which is defined as those who live and work in the area. Please do not use this road if you do not have to, as contractors have to stop their work to allow for passage when cars go by, slowing the recovery process.
NC DOT updates on Highway 64: A temporary road is expected to be open between Chimney Rock and Hendersonville was extended to June 30, 2027 (YES, 2027). For more information, visit NC DOT’s Drive NC link: https://drivenc.gov/?type=incident&id=715074
Update from Gerton Fire and Rescue: "We would like to impress that these roads are for local traffic only. We have had a surge in tourists over the last few weeks. Please stay out of the gorge if you do not live there and let them work." Gerton Fire Chief.
Directions to Lake Lure from I-26: Lake Lure is just 14 miles from I 26: At the first exit in North Carolina, Exit #67 (Columbus and Highway 108), turn right onto Highway 108 East. Follow 108 East for approximately 6 miles to the intersection of Highway 108 and Highway 9 (a traffic stoplight). Turn left onto Highway 9 North. Go 8 miles to the stop sign (Lake Lure will be in front of you).
Proctor Road: The project is complete. The road is open. The next step is repaving the road but it will be passable during this phase of the work. A barrier will be installed for safety. Thank you to the residence for their patience as this work was completed.
Boys Camp Road Bridge: LaBella Associates are designing the Boys Camp Road Bridge. The design is expected to be completed by the late fall. Once the design is complete the project will go out for bid.
MEETING THE MARK
The following is a summary of the high-level meetings from the past two weeks.
-
Town Council Storm Recovery Meeting: Town Council met with Town leaders to discuss and move forward the ongoing work of the storm recovery. Updates are included throughout this report.
-
Town Council Regular Meeting: Town Council held their Regular Meeting on 10/14/25. Updates are included throughout this report but you may review the meeting summary here.
-
Playground Planning Meeting: Town officials met with KaBoom representatives to plan and build the new playground equipment along with over 100 volunteers!
-
FEMA Meeting: Town Officials continue to meet with FEMA Officials to advance the complex public assistance projects.
-
Departent of Commerce Meeting: Town officials met with Department of Commerce Officials to discuss Community Development Block Grant opportunities.
-
Rutherford County Tourism Development Authority (TDA) Board Meeting: Town officials participated in the bi-monthly Rutherford COunty TDA Meeting and cnfirmed that the $185,000 donation that was given to TDA could be used for the construction on the Lake Lure FIre Station II construction project.
-
WNCCMA Meeting: Town Manager participated in the Western NC City and County Managers Meeting.
-
Construction Pplanning Meeting: Town Officials met to review the next steps in remodel of Lake Lure Fire Station II.
-
NC Works Conference: Mayor Pritchett participated in a panel discussion at the NC WOrks Conference in Greensboro, NC.
-
American Flood Coalition: Town Officials participated in an American Flood Coalition meetng in Blowing Rock NC.
-
LaBella/ICF Meeting: Town officials met with LaBella Engineers and ICF representatives to review and discuss related claims involving the sewer system.
-
Media: Town Officials worked with PBS to plan for filming in Lake Lure next week.
-
Lake Lure Hazard Mitigation Grant Program (HMGP) Meeting: Town officials met to review and discuss the Town's HMGP status through FEMA. HMGP provides funding to governments to develop hazard mitigation plans and rebuild in ways that reduce or mitigate future disaster losses in their communities.
-
Media: Town Offcials worked with The Daily Courier on an article on the upcoming Arts and Crafts Festival. .
-
Town Council Work Session and Action Meeting: Town Council held their Work Session and Action Meeting on 9/24/25. Updates are included throughout this report. You may download a summary of the meeting here.
-
Media: Mayor Pritchett participated in an interview with the Daily Courier on the topic of the new playground equipment planned for Morse Park.
-
ICF Meeting: Lake Lure Town Officials met with ICF officials to discuss the progress, status, and information required for FEMA reimbursements in the 4th quarter since Hurricane Helene.
-
Media: Town Officials worked with the Asheville times on an upcoming article they are working on related to the lake retoration.
-
Schnabel Engineering Meeting: Town officials met with Schnabel Engineers and ICF representatives to discuss FEMA reports.
MORSE PARK TEMPORARILY CLOSED
To ensure the work can be completed safely and on schedule, Morse Park will be temporarily closed.
- We cannot provide a timeline for this project at this time, but weekly updates will be provided here.
- The Town of Lake Lure understands the importance of Morse Park to our community, and we appreciate your patience during this temporary closure.
- The Playground equipment was installed October 15, 2025 in preparation for reopening the park, but will not be accessible until Morse Park reopens.
- Hopefully, Morse Park will reopen in the late fall of 2025.
LAKE LURE DAM
-
Reservoir Drain: The reservoir drain project at the dam has allowed the Town to lower the lake to 30 feet as planned for the ongoing lake restoration work. The drain is closed at times if work is taking place behind the dam to ensure safety. Otherwise, it is open to allow a flow of water in the river.
-
Field Testing for Replacement Dam: Schnabel Engineering completed the field testing for the replacement dam. The final report has been submitted to the NC Department of Environmental Quality Dam Safett Office for review and approval. The Town received a FEMA HHPD grant for $380,000 to support this project.
-
Tainter Gate Repairs: Schnabel Engineering conducted an inspection of the Tainter gates. Based on their findings, the Town Council approved a work order for the design of necessary repairs, including seal repair. Schnabel Engineering is developing the scope of work, which includes the design of repairs to the dam’s concrete ogee (allows for uncontrolled flow over the top of the reservoir) and the installation of new rubber seals along the base of the Tainter gates. This project will be completed when the lake comes back up a bit, in the winter of 2025-26.
-
Grant to Support Design for Replacement Dam: We hope to begin design work for the replacement dam in the fall of 2025. We are hoping to receive confirmation on a FEMA High Hazard Potential Dam (HHPD) Grant to support the cost of this project. We were intially advised that the Town should receive a confirmation on this funding in the coming weeks; however the Government shutdown is delaying the grant.
-
Boom: Schnabel is designing a boom for the dam area.
-
Recognition: We are also proud to share that the Town has been selected to receive the 2025 Southeast Regional Dam Safety Award from the Association of State Dam Safety Officials (ASDSO). This recognition highlights the Town’s efforts on the Low-Level Outlet Project, its proactive response to Hurricane Helene, and its ongoing commitment to securing funding for a long-term dam solution.
WATER AND SEWER SYSTEM
West End Sewer System Project: The West End Sewer project will be finished soon. We should have the new 828 restaurant, the hair salon, and those on Buddy Lane connected by next week.
Sewer Replacement Project: Town Officials meets regularly with LaBella Engineering to review current task orders and progress on the sewer replacement project. Upcoming phases for the sewer project were just approved by the NC Department of Environmental Quality (NC DEQ) in an Engineering Report/Environmental Information Document (ER/EID). In preparation for upcoming phases of the project, the Town has also begun communicating with several residents to discuss potential easement needs.
The Town continues to work closely with the North Carolina Division of Water Infrastructure (NC DWI) and neighboring communities to pursue a grant that will fund a study on the potential impacts and benefits of a regionalized sewer system.
Additionally, the Town is collaborating with NC DWI to secure supplemental State Revolving Fund (SRF) financing, which is expected to include principal forgiveness. You may ead more here.
Sewer System Maintenance: Public Services continues to work to maintain the larger sewer system. Planning and design work will be proceeding in Sunset Cove, Tryon Bay, Snug Harbor, and Grey Logs Cove in anticipation of future funding. The Town has applied for FEMA funding to support restoration of the system. We are awaiting a decision regarding this request and updates will be provided as new information becomes available.
Mainline Sewer Repair: The Town is actively trying to address the mainline issue, it is not fully resolved, but there is enough flow that it is currently operational.
Washburn Tank Cover Replacement: Successfully completed the replacement of 20 water tank system lid, improving system integrity and safety. The Town has been working with LaBella Associates to design and replace the 20,000-gallon tank cover for the Washburn Tank. The Authorization to Construct was issued on December 7, 2023, following the Water Tank Reconditioning Plan approval on November 7, 2023.
- Although the project experienced delays due to Tropical Storm Helene, progress has continued.
- The engineer’s certification was issued, and a request for final approval was submitted to NCDEQ on June 17, 2025.
- Water testing was completed and yielded satisfactory results.
- Final approval from NCDEQ was issued on July 11, 2025, officially marking the project's completion.
Lift Station: The system is operational and online
Waste Water Treatment Plant: The Waste Water Treatment Plant (WWTP) is operational, but we have submitted a request to FEMA for a replacement treatment system. We are awaiting a decision regarding this request and hope to relocate the system out of the flood zone.
FEMA Public Assistance (PA) is working with the Town to move the permanent repairs for the Wastewater Treatment Plant (WWTP) forward as a Version 0 project, which allows the Town to receive funding for architectural and engineering (A&E) services.
- A task order with LaBella was previously approved by Town Council, contingent upon FEMA funding.
- Once this project is officially obligated, LaBella Associates will be able to proceed with the design work.
It is the Town's position—and that of the engineers at LaBella Associates, that the appropriate permanent repair for the WWTP is a full replacement of the facility, rather than piecemeal repairs to the existing plant, which is not feasible.
Utility Locate Responses: Responded to 26 utility locate requests through the 811 system, ensuring safe excavation and infrastructure protection across multiple work zones.
Are we applying for grants to assist with expenses? Yes! LaBella Associates are working with Town officials to prepare an application for the Helene Recovery State Revolving Fund (SRF), which offers the potential for up to $5 million in principal forgiveness, if awarded. The SRF is a program that provides low-interest loans for water and wastewater infrastructure projects.
Deep Water Ramp: The deep water ramp was planned for the Rumbling Bald area; however this location was not possible. The Town is seeking an alternative site for the ramp.
PRIVATE WELLS
If you have a private well and lowering the lake has affected your well, then lake water may have been infiltrating your aquifer.
- The first signs are sedimentation in your water, then air introduction to your system.
- The Town anticipates the lake will continue to be lowered for several more weeks.
- We do not currently have a date for refilling the lake as it is dependent upon the silt/sedimentation/debris removal being overseen by the USACE.
- It is recommended that individuals experiencing these indicators consult a well company.
- Sedimentation can be filtered, but air usually means you need to dig a deeper well to retrieve water from a protected aquifer below the clay or rock layer.
The Town of Lake Lure consulted with the North Carolina Department of Environmental Quality regarding this matter to see if they could be of any assistance. They provided the following link for individuals seeking financial assistance with their wells: Water Well Trust. You may learn more about applying for this assistance here.
Additionally, here are resources for assistance with testing and disinfecting personal wells.
1) Foothills Health District: Please click on the following link for Emergency Drinking Water Well Disinfection Procedures
http://www.foothillshd.org/images/forms/4000/4001/FoothillsHealth_WellWa...
2) Broad River Water Authority: 828-286-0640 https://www.ncbrwa.com/
3) James & James Environmental Management, Inc.: 828-697-0063 https://www.facebook.com/jamesandjames1992/
CONTRACTOR INFORMATION
Only approved contractors may access properties from the lake, by boat or barge, but any contractor or property owner may work on lake structures (with permits) if accessing from land. This includes sea wall construction or restoration (again, with required permits). You may emailkmartin@townoflakelure.com"> kmartin@townoflakelure.com with any questions.
Click here for additional information on contractors.
DAMAGED LAKE STRUCTURES
The Community Development Department has created a map showing most of the seriously damaged lake structures, over 100 boathouses. These are properties that the owners agree to the demo of the boathouse. If you have damages, be aware that you will need to contact the Community Development Department about permitting for repairs or replacement. Permits are being issued and work is being done on lake structures now, but all work must be authorized.
- For property owners who signed up for the no-cost demolitions by the Army Corp, they are working on their plan now and we will notify you as we have more specific timing information.
- We have confirmed that, if you are signed up for the condemnation/removal program, they will be contacting you individually for a “right of entry” agreement prior to beginning the work.
- Town officials are working with the USACE to determine their timeline for this process, likely in the winter months.
Update 10/17/25:
- The Town has received 9 denials for boathouse removal by FEMA. We expect to have denials for the remaining 20 boathouses as well. We are continuing to appeal this decision and will update property owners once more information is available.
- Please contact Community Development Staff for more information about the Army Corp program, as well as your permitting, at kmartin@townoflakelure.com or 828-625-9983, x 135.
FINANCIAL SUPPORT/APPLICATIONS
The following chart illustrates the financial support the Town of Lake Lure is currently seeking, in addition to Federal and State Funding requests that have been made on behalf of the Town through our political representatives (disaster management planning experts) and Hager Strategic Solutions (lobbyist). They are assisting the Town with post-disaster federal funding applications and requests to expedite our recovery process.
There are now 34 projects that have been submitted to FEMA for consideration of funding and the Town is awaiting their review and feedback.
8/13/25 update: Nine FEMA-funded projects have been obligated. The Town has received $2,325,171.92 for seven of these, and two additional reimbursements totaling $38,212.80 are pending. Delays persist for projects over $100,000, and staff have begun contacting elected officials to address these concerns.
8/20/25 update: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.
Several other projects are currently under review by FEMA. While the process continues to move slowly, we are seeing progress, and these projects are inching closer to obligation.
- Diving Operations at the Dam ($700K range)
- Flowering Bridge Demo: Version 0 - will have to argue costs.
- Community Center/Welcome Center: Came back at $160,000, which is far too low.
- Marina Docks
- Lake buoys and booms.
9/10/25 update: Newly received funding:
- $13,255.75 – Category A: Dumpster rentals
- $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility
- $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work
9/18/25 update: $2.8 million obligated for Flowering Bridge Demo: Version 0 - As noted above, Town officials will have to argue costs. The $2.8 million currently obligated represents a preliminary estimate, intended to provide the Town with initial funds to cover demolition costs already incurred and to support efforts to develop accurate replacement cost estimates. The Town is actively pursuing discussions with FEMA to negotiate a fixed cost offer based on the true cost of replacement. It is the Town’s intention that these valuable funds be directed toward priority recovery projects that will strengthen and restore our critical infrastructure. Read here for additional details.
Organization |
Funding Request |
Status |
State of NC-DEQ-Water (Loan with potential forgiveness) |
$3,000,000 |
Application under review |
FEMA-Revenue Replacement (Loan with potential forgiveness) |
Up to $5,000,000 |
Financial data under review; additional data being provided |
FEMA reimbursements |
Up to $7,500,000 |
5/2/25 Update: 5 projects now obligated for a total of $3,224,564.61. ·$862,186.69 Received 4/25 for a Category A (Debris Removal) 5/18/25 Update: $754,185.81 (anticipated 5/25) for a Category B (Emergency Protective Measures) (payment received) 5/23/25 Update: Received a check for $65,390.00 for Category A Town Wide Vegetative Debris Removal from ROW and Public Property. A new project was obligated for $118,323.67 for Category B Temporary Hydroelectric Plant Emergency Repairs. (payment received) 6/23/25 Update: Received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C); 8/4/25 Update: Received $8,250 for Temporary Town Hall Facility (Category B); Received $13,255.75 for Lake Lure Dumpster Rentals (Category A); 9/10/25 update: Newly received funding: $13,255.75 – Category A: Dumpster rentals; $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility; $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work |
DEQ-ARPA Reimbursement (non-storm related) |
Up to $3,000,00 |
Submission under review |
Private Donations |
Up to $90,000 |
Deposited; being held for future disbursement under discretion of Town Council |
Other Revenues and Payments from Insurance proceeds and claims |
Up to $5,000,000 |
50% has been approved for release 1/7/25 Update: 50% received. 1/31/25 Update: $1.3 million insurance payment for damage to Town Hall. |
NC Treasurer Cash Flow Loan |
$3,423,122.89 |
3/21/25 Update: Received 6/23/25: The Town was offered an additional $2.8 million in cash flow funds from the State Treasurer. A recommendation regarding this offer will be made to Town Council for consideration. 6/25/25: Town Council approved the loan. 7/29/25: Received a $2.8 million dollar loan disbursement this week from the NC Treasurer |
MONETARY DONATIONS
Our community, along with many of our neighbors, has been devastated by the catastrophic flooding caused by Hurricane Helene. The Town of Lake Lure, NC is deeply grateful for the support our community has received. We have had numerous requests to establish a mechanism for financial donations. Please click on the following link to donate to the Town of Lake Lure Storm Recovery Fund.
https://www.paypal.com/ncp/payment/WXB6HYYE8Y5PJ
Additional options for monetary donations include the following:
- Hickory Nut Gorge Outreach: https://hickorynutgorgeoutreach.org/one-time-donation/
- Hurricane Helene – Força Foundation: https://forcafoundation.com/hurricane-helene/
- RHI Legacy Foundation will match any donation up to $50,000 at www.rhilegacyfoundation.com
- Restore Lake Lure Fundraising Campaign: https://www.restorelakelure.com/ The Restore Lake Lure campaign seeks to bridge the gap between governmental support and personal sacrifice."
- The Foundation For Lake Lure/Chimney Rock Area Businesses: https://foundation4lakelurechimneyrock.com/home\
- United Way of Rutherford County at www.unitedwayofrutherford.org
STORM RECOVERY ACCOMPLISHMENTS
Swift evacuation by first responders saving countless lives 9/27/24.
Countless rescues first responders during and following Hurricane Helene.
Coordination with the Rutherford County Emergency Management during and throughout the storm.
Dam assessment and stabilization immediately following the storm event 9/27/24-9/29/24.
Communication with the Rutherford County EOC and FEMA for recovery immediately following the storm.
Coordination with volunteer groups to provide hot meals, shower services, restrooms, and handwashing stations in strategic locations by 10/1/24. Christian Aid Ministries served 8,080 hot meals and assisted 43 homeowners with clean-up of their homes and property. There were 164 volunteers and they spent 2,457 hours assisting our community!
Creation of donation stations to disseminate supplies throughout town by 10/1/24.
Cleared Highways and Town roads within days of the storm.
Restoration of water service throughout Town with water quality testing allowing Boil Advisory lifted 10/14/24 and 10/16/24 respectively.
Rapid repair of power services throughout Town by Duke Power and REMC.
Establishment of temporary communications systems through Starlink (10 systems) and Cell on Wheels with AT&T and Verizon 10/16/24.
Replacement of fiber to re-establish internet and cell service to the area 10/18/24.
Repair to the left abutment of the Dam by 10/27/24 with 2,494.64 tons of material securing the area.
Army Corps of Engineers contract signed with AshBritt to oversee lake debris and silt/sedimentation removal during a 160 day period of performance beginning 10/28/24. Debris removal began 11/4/24.
Emergency repairs to the sewer system completed, allowing "no flush order" to be lifted for most on 10/28/24.
Reopening of the Dam Bridge on Buffalo Shoals Road on 10/31/24.
Dittmer Watts Nature Trails and a portion of the Green Space reopened on 11/19/24.
Pressure Reducing Valve Construction in Lake Lure Town Center successfully completed 11/22/24.
The Boys Camp Road Temporary Bridge was completed 11/26/24.
As of 1/23/24, Over 32,782 CY of debris were removed from the right of way, 27,669 tons of sediment and silt have been removed from Town and the Parks, 24,558 cubic yards (CY) of debris have been removed from the Lake.
1/10/25: Burnt Ridge Landslide repair completed.
1/7/25: 50% of insurance payments received.
1/22/25: Contracted with lobbyist Hager Strategic Solutions (lobbyist).
1/22/25: Proclamation to open Chimney Rock State Park as soon as possible to bring in tourism to the area and strengthen the economy.
1/31/25: Culvert repair on Hummingbird Cove completed.
1/31/25: $1.3 million insurance payment received for damage to Town Hall.
2/11/25: Waste Water Treatment Plant is now operational. Repaired 3 water leaks throughout the water system
2/14/25: Storm drain box culvert repaired at corner of Memorial Hwy and Charlotte Dr
2/19/25: Youngs Mountain Trail landslide repaired
2/21/25: Green Space drainage repairs completed, grass replanted, and dry creek beds put into place.
2/28/25: The Town of Lake Lure and all those in areas code 28746 are eligible to apply for a free option for debris removal program through the USACE.
3/7/25: Debris removed from Morse Park trails and grass replanted in that area.
3/14/25: FEMA approval of the mission assignment for Lake Surface Debris, silt, and sedimentation removal through FEMA and the US Army Corps of Engineers.
3/18/25: Community Forum held with FEMA, USACE at The Lakeside Terrace with approximately 200 attendees.
3/18/25: United Way presented Fire Chief Dustin Waycaster a check for $50,000 for a new heart monitor for Firefights/AMTs.
3/27/25: Reservoir Drain Valve Installation complete.
4/24/25: 371 +/- boats that have been removed from the lake.
4/25/25: Reopened the East entrance to Morse Park.
5/2/25: $862,186.69 Received 4/25 for a Category A (Debris Removal)
5/11/25: $754,185.81 Received for a Category B (Emergency Protective Measures)
6/12/25: New seawall completed at the Lake Lure Gazebo
6/13/25: New pavers replaced broken and missing pavers in the Morse Park walkway and in front of the Lake Lure Beach.
6/17/25: The Lake Lure Beach was replenished with fresh sand.
6/23/25: The Town received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C)
6/25/25: Cash flow loan approved for $$2.8 million.
6/27/25: Downslide repaired on Angler's Way.
7/21/25: Repairs on Boys Camp Road completed.
7/21/25: Debris and silt/sedimentation removal from the Rumbling Bald Beach and Marina are complete.
7/28/25: Town Hall relocated to temporary office space in The Landings. The official opening date for the public is 8/1/25.
7/28/25: The Town received the $2.8 million loan disbursement this week from the NC Treasurer.
8/7/25: Received $8,250 from FEMA for Temporary Town Hall Facility (Category B); Received $13,255.75 from FEMA for Lake Lure Dumpster Rentals (Category A).
8/13/25: Silt/sedimentation removal began in Washburn Marina and coves around the lake, like Tryon Bay.
8/20/25: Asheville Tennis Association presented the Town of Lake Lure with a check for $19,000 to help rebuild our future tennis/pickleball courts.
8/20/25: The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.
8/20/25: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.
8/30/25: West end Sewer System largely restored.
9/10/25: FEMA funding received: $13,255.75 for Dumpster rentals, $28,531.78 for Temporary Relocation Costs – Town Hall Facility, $9,681.02 for Municipal Water Supply Damage
9/19/25: Proctor Road restoration project complete.
9/26/25: The Town received a total of $380,000 in a FEMA HHPD Grant for the Field Investigation Project that was recently completed.
9/27/25: Lake Lure and Chimney Rock came together to hold a one year Commemoration Ceremony
10/15/25: The new KaBOOM! Playground equipment was installed 10/13/25 - 10/15/25 through a grant from BCBS. Over 100 volunteers participated in the installation.
ONGOING
- Emergency repairs to the sewer system.
- Constant removal of silt, sedimentation, and debris from the lake and roadways.
- Removal of condemned boathouses and personal property debris removal.
- Town officials are working to develop a comprehensive plan for future prosperity in the Town of Lake Lure.
WHAT’S OPEN IN THE TOWN OF LAKE LURE!
While visitors should be mindful of ongoing recovery efforts, several local businesses and recreation areas have reopened. There are a number of attractions that are open in the area. Lake Lure hotels, lodges, bed & breakfasts, and our amazing restaurants are open for business! Our local businesses greatly appreciate your patronage! Please visit the area and encourage others to visit as well.
Download the 2025 Travel Guide here.
Please visit the Local Restaurant Guide
Download the Falling Back in Love with Lake Lure and Chimney Rock Passport
And here are some of the amenities that are currently open to the public.
- Morse Park Walkway and the Lake Lure Gazebo (temporarily closed during silt removal in Marina Cove.)
- Dittmer-Watts Nature Trails
- Lake Lure Green Space
- Pool Creek Picnic Park
- Youngs Mountain
- Rumbling Bald Golf Courses
- Chimney Rock State Park – Rumbling Bald Access
- Chimney Rock State Park – Now open daily by reservation - Click here to reserve your tickets!
Additionally, horseback riding is available in the area along with zip lining, escape rooms, a candy cabin, and so much more!
Buffalo Creek Park/Weed Patch Mountain Trail/Upper Boulders Trail: Ongoing work is also taking place at Buffalo Creek Park, Weed Patch Mountain, and the Upper Boulder Trails by the National Guard, Carolina Climbers Coalition, Rutherford Outdoor Coalition, EcoForesters, and AmeriCorps. We cannot thank them enough for their time and support! Progress continues to be made on Upper Boulders Trail, and a small section may be opening soon. The Town will receive a grant of $50,000 to assist with restoration. Please stay tuned for updates!
Upcoming Events:
-
10/18-19/25: Hickory Nut Gorge Outreach Fall Arts and Crafts Festival
-
10/18/25: Lake Lure Artist's Show and Sale
-
10/28/25: Comprehensive Planning Virtual Public Input Session (4-6 PM)
-
10/31/25 – 11/1/25: Lake Lure Classica’s Haunted Trail (6-9 PM)
-
11/5/25: Comprehensive Planning Public Input Session at The Landings (4-7 PM)
-
11/11/25: Lake Lure Veterans Day Program on the Rumbling Bald Terrance (9 AM)
QUESTIONS/SUGGESTIONS
You may review previous Storm Recovery Updates in Town News at www.townoflakelure.com
For questions or suggestions, please email Communications@townoflakelure.com