Lake Lure Storm Recovery Updates and More - 10/31/25
Please take a moment to watch the video shot last week in Lake Lure by Newsmax. This video was shown on their national broadcast. The video features Community Development Director Mike Williams, Fire Chief/Emergency Management Coordinator Dustin Waycaster, Mayor Carol Pritchett, and Commissioner Dave DiOrio. They provide an update on Lake Lure's storm recovery one year after Hurricane Helene.
STATUS OF LAKE RESTORATION
The U.S. Army Corps of Engineers (USACE), through a FEMA mission assignment, continues recovery work in Lake Lure This work is being conducted under the Direct Federal Assistance (DFA) contract, which has been extended through November 20, 2025.
- This extension allows additional time to complete the remaining work and ensure the lake is safe, stable, and navigable.
- The Town of Lake Lure remains deeply grateful for the extraordinary work that has been accomplished and for this extension.
- The lake restoration mission has been extensive and complex.
- Over time, the scope of work expanded from surface debris removal to subsurface debris and sediment management, with the goal of restoring the lake as closely as possible to pre-storm conditions.
- To date, USACE teams have removed more than 1.2 million tons of debris from the lake.
- Contractors have transitioned from excavating and hauling sediment to restoring and stabilizing work areas.
- This includes removing temporary haul roads, redistributing sediment to restore pre-event conditions, and grading areas to proper and stable elevations.
- Sediment is being safely redistributed to support shoreline stabilization except for any large debris that may be found within the sediment.
- This work is guided by a USACE hydrology and hydraulics expert with experience on large-scale projects.
- Trucking and barge operations have concluded, as these methods are no longer required for the remaining work.
SHORELINE DEBRIS
- Town Officials are aware that shoreline debris remains around the lake and in several coves.
- The Town of Lake Lure is working to develop a plan to pick up shoreline debris that remains.
- Please stay tuned for additional information as this plan is formulated.
WHAT IS THE LAKE LEVEL
The Lake Level is currently at about 970 Mean Sea Level (MSL) after the rain this week.
- Full pond in Lake Lure is 990.5 MSL.
- The current plan is to let the lake naturally rise to approximately 975 MSL.
- The speed at which the lake will refill to this level is dependent upon the weather.
- The plan is to maintain the lake level at about 975 MSL until further notice.
- Any changes in lake levels beyond this point will be posted in Town News at www.townoflakelure.com.
HOW LONG WILL THE LAKE BE DOWN?
We are unable to specify the length of the drawdown period at this time.
- When a change in the lake level is planned, it will be posted in Town News at www.townoflakelure.com.
- Throughout the lake drawdown, Town engineers and staff will be scheduling work and inspections on the dam and the sewer system to maximize this opportunity to accomplish projects with the lower lake levels. See details later in this report under the dam and sewer system sections.
CAN WE ACCESS THE LAKE?
The Town of Lake Lure and all businesses are open and welcoming visitors; however, the lake itself remains closed to all unauthorized personnel.
- Lake Lure remains a Federal Work Site.
- Do not enter the lake or the lakebed for everyone's safety, and to avoid fines.
WHEN WILL THE LAKE REOPEN?
The lake restoration is a dynamic process so the date for reopening the lake is uncertain.
- The Town of Lake Lure remains hopeful that we will be able to reopen the lake in the late spring of 2026.
- You may read the Town's Press Release on the reopening timeline here.
LAKE LURE WATER QUALITY
We are pleased to report that the latest results (October 2025) are all within acceptable limits.
- You may review the updated spreadsheet, which illustrates all the water sample data received by the Town of Lake Lure.
- For questions, please contact Communications@townoflakelure.com.
DEMOLITIONS
Town officials have been advised of the following planned demotions:
- The Geneva
- The Morton House
- A house on Angler's Way
The timing of these demolitions is uncertain.
CELL TOWER UPDATES

Cell Tower Construction 10/22/25
For those who have experienced challenges with phone service in Lake Lure, you can see the progress on the cell tower here!
- The location of the cell tower is off Boys Camp Road on the old campground property.
- Tillman Infrastructure is building the tower and will own it.
- They will lease antenna space to cellular service providers and AT&T will be the primary provider.
- Verizon has leased the next highest space and T-Mobile will be the third provider.
- The antenna is expected to be in place this winter.
- It is anticipated that the tower will be installed by December 8, 2025.
- We expect to have improved cell coverage by the first of 2026.
KEEP IT IN THE ROAD!
Memorial Highway (64/74) between Lake Lure and Chimney Rock is open. NC Department of Transportation (NCDOT) has been repaving portions of 64/74 in Lake Lure and the new roadways are greatly appreciated!

Highway 64/74A Beyond Chimney Rock Village: Highway 64/74A heading West beyond Chimney Rock Village remains closed to the public at large. It is open to "locals", which is defined as those who live and work in the area. Please do not use this road if you do not have to, as contractors have to stop their work to allow for passage when cars go by, slowing the recovery process.
NC DOT updates on Highway 64: A temporary road is expected to be open between Chimney Rock and Hendersonville was extended to June 30, 2027 (YES, 2027). For more information, visit NC DOT’s Drive NC link: https://drivenc.gov/?type=incident&id=715074

Update from Gerton Fire and Rescue: "We would like to impress that these roads are for local traffic only. We have had a surge in tourists over the last few weeks. Please stay out of the gorge if you do not live there and let them work." Gerton Fire Chief.
Directions to Lake Lure from I-26: Lake Lure is just 14 miles from I-26: At the first exit in North Carolina, Exit #67 (Columbus and Highway 108), turn left onto Highway 108 East. Follow 108 East for approximately 6 miles to the intersection of Highway 108 and Highway 9 (a traffic stoplight). Turn left onto Highway 9 North. Go 8 miles to the stop sign (Lake Lure will be in front of you).
From Asheville: From I-26 - Take Exit #67 (Rutherfordton - Highway 108), once you exit, turn left onto Highway 108 East. Follow 108 East for approximately 6 miles to the intersection of Highway 108 and Highway 9 (a traffic stoplight). Turn left onto Highway 9 North. Go 8 miles to the stop sign (Lake Lure will be in front of you).
Proctor Road: The project is complete and the road is open. Paving is scheduled for 11/3/25. Jersey Barriers will be installed. Thank you to the residence for their patience as this work was completed.
Boys Camp Road Bridge: LaBella Associates are designing the Boys Camp Road Bridge. The design is expected to be completed by the late fall. Once the design is complete the project will go out for bid.
Charlotte Road: Town officials are obtaining a quote for repaving Chatlotte Drive. Updates will be provided here once a timeline has been confirmed.
MEETING THE MARK
The following is a summary of the high-level meetings from the past two weeks.
-
Town Council Storm Recovery Meeting: Town Council met with Town leaders to discuss and move forward the ongoing work of the storm recovery. Updates are included throughout this report.
-
Dredging & Individual Permit Meeting: Town Officials met to plan for future dredging and permitting requirements.
-
FEMA Meeting: Town Officials continue to meet with FEMA Officials to advance the complex public assistance projects.
-
Town Council Work Session and Action Meeting: Town Council held their Work Session and Action Meting on 10/22/25. Updates are included throughout this report but you may review the meeting summary here.
-
Economic Development Administration (EDA): Town officials met with EDA officials to discuss the grant application process.
-
Lake Lure Dam Meeting: Town officials met with engineers from Schnabel Engineering to discuss the spillway crest repairs project.
-
Marina and Boardwalk Bid Review: Town Officials met to review and evaluate the Marina and Boardwalk replacement bids.
-
USACE Meeting: Town Officials met with USACE to discuss the ongoing lake restoration.
-
The following Board Meetings were held: ABC Board, Zoning and Planning Board, Board of Adjustments/Lake Structures Appeals Board
-
LaBella/ICF Meeting: Town officials met with LaBella Engineers and ICF representatives to review and discuss related claims involving the sewer system.
-
Media: Town Officials worked with PBS to plan for filming in Lake Lure next week.
-
Lake Lure Hazard Mitigation Grant Program (HMGP) Meeting: Town officials met to review and discuss the Town's HMGP status through FEMA. HMGP provides funding to governments to develop hazard mitigation plans and rebuild in ways that reduce or mitigate future disaster losses in their communities.
-
Media: Town Offcials worked with The Daily Courier on an article on the upcoming Arts and Crafts Festival. .
-
Town Council Work Session and Action Meeting: Town Council held their Work Session and Action Meeting on 9/24/25. Updates are included throughout this report. You may download a summary of the meeting here.
-
Media: Town Officials conducted interviews with reporters from Newsmax.
-
Interview: Mayor Pritchett participated in an interview with Prinston University.
-
ICF Meeting: Lake Lure Town Officials met with ICF officials to discuss the progress, status, and information required for FEMA reimbursements in the 4th quarter since Hurricane Helene.
-
Media: Town Officials worked with a team from PBS to film on the various trails in Lake Lure.
-
Schnabel Engineering Meeting: Town officials met with Schnabel Engineers and ICF representatives to discuss FEMA reports.
IN THE NEWS
The following is a summary of some of the relevant news coverage Since the last report.
1) Nearly 500 acres purchased for vast nature preserve near Chimney Rock, Lake Lure

RUTHERFORD COUNTY, N.C. (WLOS) — Nearly 500 acres of land have been purchased by Conserving Carolina for a vast nature preserve located near Chimney Rock State Park.
According to an Oct. 30 news release, Conserving Carolina purchased 483 acres of mountainous land North of Lake Lure. The tract is the last major piece in a 2,669-acre protected wilderness adjacent to Chimney Rock State Park, the release said.
“At the end of the day, we protected about 75% of a state natural area that is rated excellent for wildlife habitat, which is the highest possible rating," Assistant Director for Programs with Conserving Carolina Rebekah Robinson said in the release.
Now, the full 2,669 acres is protected — over half of it as the Town of Lake Lure’s Buffalo Creek Park and the rest as the Joel Ridge Nature Preserve, owned by Conserving Carolina, the release said.
2) Day 2 of 2025 government shutdown: North Carolina's recovery from Hurricane Helene unaffected so far
The government shutdown has not yet impacted FEMA's recovery work in western North Carolina, Governor Stein confirmed. Watch the newscast here.
CHARLOTTE, N.C. — It's day two of the government shutdown, as Republicans and Democrats have not reached a deal to fund the government yet. It's impacting a lot of federal operations, but some are wondering about potential impacts in western North Carolina.
A year ago, Hurricane Helene tore through the region and left around $60 billion in damage. Cleanup continues, but how will this federal shutdown impact recovery efforts?
...On the first day of the shutdown, Governor Stein confirmed on X that FEMA operations, like debris removal, will not be impacted by the shutdown, at least for right now.
He also called upon the Trump administration to grant an exception for all recovery-related efforts in western North Carolina.
On Wednesday, North Carolina Congressman Tim Moore went to Lake Lure and Chimney Rock to see if recovery efforts are continuing. He said work will continue unless the shutdown continues for weeks.
“I was glad to see that work has not stopped,” he said. “I'm told that if it gets close to 30 days, that's when it will be a problem. We should not see any issues if it gets resolved, but I don't want to take the chance of that."
The last shutdown in 2018 lasted over 30 days.
Several towns in the region are waiting for FEMA to reimburse them for funds spent after Hurricane Helene. However, that could be slowed down even more because of the shutdown.
Contact Meghan Bragg at mbragg@wcnc.com and follow her on Facebook, X and Instagram.
Download WCNC+ on your Roku, Amazon Fire TV, Apple TV or Samsung device, and stream the news that impacts you for free.
3) Governor Stein Announces Nearly $18 Million in Contributions for North Carolina Food Assistance
Thursday, October 30, 2025
Today Governor Josh Stein announced that the State of North Carolina will grant $10 million to local food banks across the state.
Today Governor Josh Stein announced that the State of North Carolina will grant $10 million to local food banks across the state. The State is joined by AmeriHealth Caritas, which will give $5 million, The David & Nicole Tepper Foundation, which will accelerate $2.5 million from a previously announced $10 million gift, and other donors. These announcements come as food banks prepare for an influx of need following the U.S. Department of Agriculture (USDA)’s decision to suspend the distribution of Supplemental Nutrition Assistance Program (SNAP) benefits for November.
“With the help of generous partners, North Carolina is taking action to keep families fed,” said Governor Josh Stein. “Shoring up our state’s food banks will serve as a critical, but fleeting, lifeline for families in need, and I hope other North Carolina organizations will also step up in this time of need. Whether it’s paying our military, ensuring no child goes hungry, or lowering health care costs, leaders in Washington need to come together immediately to find a bipartisan solution that provides long-term stability for millions of Americans.” Read more here.
4) Piece of memorial to beloved pets recovered in Helene cleanup at Lake Lure
LAKE LURE, N.C. (FOX Carolina) - The Flowering Bridge organization in Lake Lure said that a FEMA contractor found a piece of a beloved memorial while cleaning the area. Watch the newcast here.
The organization reports that Leyon Kerklin, while working on cleaning the lake bed, noticed a dog collar in the sediment. A closer inspection revealed a section of the Rainbow Bridge covered in dog collars.
The Rainbow Bridge was a project meant to allow grieving pet owners to remember their beloved animals as they placed collars on the bridge in their pet’s memory.
Kerklin’s wife, Evelin, reached out to the Flowering Bridge organization and helped return 238 collars.
MORSE PARK TEMPORARILY CLOSED
To ensure the work can be completed safely and on schedule, Morse Park will be temporarily closed.
- We cannot provide a timeline for this project at this time, but weekly updates will be provided here.
- The Town of Lake Lure understands the importance of Morse Park to our community, and we appreciate your patience during this temporary closure.
- The Playground equipment was installed October 15, 2025 in preparation for reopening the park, but will not be accessible until Morse Park reopens.
- Hopefully, Morse Park will reopen in the late fall of 2025.
LAKE LURE DAM
-
Reservoir Drain: The reservoir drain project at the dam has allowed the Town to lower the lake to 30 feet as planned for the ongoing lake restoration work. The drain is closed at times if work is taking place behind the dam to ensure safety. Otherwise, it is open to allow a flow of water in the river.
-
Field Testing for Replacement Dam: Schnabel Engineering completed the field testing for the replacement dam. The final report has been submitted to the NC Department of Environmental Quality Dam Safett Office for review and approval. The Town received a FEMA HHPD grant for $380,000 to support this project.
-
Tainter Gate Repairs: Schnabel Engineering conducted an inspection of the Tainter gates. Based on their findings, the Town Council approved a work order for the design of necessary repairs, including seal repair. Schnabel Engineering is developing the scope of work, which includes the design of repairs to the dam’s concrete ogee (allows for uncontrolled flow over the top of the reservoir) and the installation of new rubber seals along the base of the Tainter gates. This project will be completed when the lake comes back up a bit, in the winter of 2025-26.
-
Grant to Support Design for Replacement Dam: We hope to begin design work for the replacement dam in the fall of 2025. We are hoping to receive confirmation on a FEMA High Hazard Potential Dam (HHPD) Grant to support the cost of this project. We were intially advised that the Town should receive a confirmation on this funding in the coming weeks; however the Government shutdown is delaying the grant.
-
Boom: Schnabel is designing a boom for the dam area.
-
Recognition: We are also proud to share that the Town has been selected to receive the 2025 Southeast Regional Dam Safety Award from the Association of State Dam Safety Officials (ASDSO). This recognition highlights the Town’s efforts on the Low-Level Outlet Project, its proactive response to Hurricane Helene, and its ongoing commitment to securing funding for a long-term dam solution.
WATER AND SEWER SYSTEM
West End Sewer System Project: The West End Sewer project will be finished soon. The new 828 restaurant, the hair salon, and those on Buddy Lane are able to connected to the system now. There are a few homes that still need a connection and Public Service irks is working with contractors to make these connections as soon as possible.
Sewer Replacement Project: Town Officials meets regularly with LaBella Engineering to review current task orders and progress on the sewer replacement project. Upcoming phases for the sewer project were just approved by the NC Department of Environmental Quality (NC DEQ) in an Engineering Report/Environmental Information Document (ER/EID). In preparation for upcoming phases of the project, the Town has also begun communicating with several residents to discuss potential easement needs.
The Town continues to work closely with the North Carolina Division of Water Infrastructure (NC DWI) and neighboring communities to pursue a grant that will fund a study on the potential impacts and benefits of a regionalized sewer system.
Additionally, the Town is collaborating with NC DWI to secure supplemental State Revolving Fund (SRF) financing, which is expected to include principal forgiveness. You may ead more here.
Sewer System Maintenance: Public Services continues to work to maintain the larger sewer system. Planning and design work will be proceeding in Sunset Cove, Tryon Bay, Snug Harbor, and Grey Logs Cove in anticipation of future funding. The Town has applied for FEMA funding to support restoration of the system. We are awaiting a decision regarding this request and updates will be provided as new information becomes available.
Mainline Sewer Repair: The Town is actively trying to address the mainline issue, it is not fully resolved, but there is enough flow that it is currently operational.
Washburn Tank Cover Replacement: Successfully completed the replacement of 20 water tank system lid, improving system integrity and safety. The Town has been working with LaBella Associates to design and replace the 20,000-gallon tank cover for the Washburn Tank. The Authorization to Construct was issued on December 7, 2023, following the Water Tank Reconditioning Plan approval on November 7, 2023.
- Although the project experienced delays due to Tropical Storm Helene, progress has continued.
- The engineer’s certification was issued, and a request for final approval was submitted to NCDEQ on June 17, 2025.
- Water testing was completed and yielded satisfactory results.
- Final approval from NCDEQ was issued on July 11, 2025, officially marking the project's completion.
Lift Station: The system is operational and online
Waste Water Treatment Plant: The Waste Water Treatment Plant (WWTP) is operational, but we have submitted a request to FEMA for a replacement treatment system. We are awaiting a decision regarding this request and hope to relocate the system out of the flood zone.
FEMA Public Assistance (PA) is working with the Town to move the permanent repairs for the Wastewater Treatment Plant (WWTP) forward as a Version 0 project, which allows the Town to receive funding for architectural and engineering (A&E) services.
- A task order with LaBella was previously approved by Town Council, contingent upon FEMA funding.
- Once this project is officially obligated, LaBella Associates will be able to proceed with the design work.
It is the Town's position—and that of the engineers at LaBella Associates, that the appropriate permanent repair for the WWTP is a full replacement of the facility, rather than piecemeal repairs to the existing plant, which is not feasible.
Utility Locate Responses: Responded to 26 utility locate requests through the 811 system, ensuring safe excavation and infrastructure protection across multiple work zones.
Are we applying for grants to assist with expenses? Yes! LaBella Associates are working with Town officials to prepare an application for the Helene Recovery State Revolving Fund (SRF), which offers the potential for up to $5 million in principal forgiveness, if awarded. The SRF is a program that provides low-interest loans for water and wastewater infrastructure projects.
Deep Water Ramp: The Town is seeking an alternative site for the ramp.
PRIVATE WELLS
If you have a private well and lowering the lake has affected your well, then lake water may have been infiltrating your aquifer.
- The first signs are sedimentation in your water, then air introduction to your system.
- The Town anticipates the lake will continue to be lowered for several more weeks.
- We do not currently have a date for refilling the lake as it is dependent upon the silt/sedimentation/debris removal being overseen by the USACE.
- It is recommended that individuals experiencing these indicators consult a well company.
- Sedimentation can be filtered, but air usually means you need to dig a deeper well to retrieve water from a protected aquifer below the clay or rock layer.
The Town of Lake Lure consulted with the North Carolina Department of Environmental Quality regarding this matter to see if they could be of any assistance. They provided the following link for individuals seeking financial assistance with their wells: Water Well Trust. You may learn more about applying for this assistance here.
Additionally, here are resources for assistance with testing and disinfecting personal wells.
1) Foothills Health District: Please click on the following link for Emergency Drinking Water Well Disinfection Procedures
http://www.foothillshd.org/images/forms/4000/4001/FoothillsHealth_WellWa...
2) Broad River Water Authority: 828-286-0640 https://www.ncbrwa.com/
3) James & James Environmental Management, Inc.: 828-697-0063 https://www.facebook.com/jamesandjames1992/
CONTRACTOR INFORMATION
Only approved contractors may access properties from the lake, by boat or barge, but any contractor or property owner may work on lake structures (with permits) if accessing from land. This includes sea wall construction or restoration (again, with required permits). You may emailkmartin@townoflakelure.com"> kmartin@townoflakelure.com with any questions.
Click here for additional information on contractors.
DAMAGED LAKE STRUCTURES
The Community Development Department has created a map showing most of the seriously damaged lake structures, over 100 boathouses. These are properties that the owners agree to the demo of the boathouse. If you have damages, be aware that you will need to contact the Community Development Department about permitting for repairs or replacement. Permits are being issued and work is being done on lake structures now, but all work must be authorized.
Update 10/31/25:
- Unfortunately, the Town has been advised that the request for demolition through the USACE has been denied.
- Town officials are working to identify alternative solutions. If you have questions regarding your property, call Community Development at kmartin@townoflakelure.com or 828-625-9983, x 135.
FINANCIAL SUPPORT/APPLICATIONS
The following chart illustrates the financial support the Town of Lake Lure is currently seeking, in addition to Federal and State Funding requests that have been made on behalf of the Town through our political representatives (disaster management planning experts) and Hager Strategic Solutions (lobbyist). They are assisting the Town with post-disaster federal funding applications and requests to expedite our recovery process.
There are now 34 projects that have been submitted to FEMA for consideration of funding and the Town is awaiting their review and feedback.
8/13/25 update: Nine FEMA-funded projects have been obligated. The Town has received $2,325,171.92 for seven of these, and two additional reimbursements totaling $38,212.80 are pending. Delays persist for projects over $100,000, and staff have begun contacting elected officials to address these concerns.
8/20/25 update: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.
Several other projects are currently under review by FEMA. While the process continues to move slowly, we are seeing progress, and these projects are inching closer to obligation.
- Diving Operations at the Dam ($700K range)
- Flowering Bridge Demo: Version 0 - will have to argue costs.
- Community Center/Welcome Center: Came back at $160,000, which is far too low.
- Marina Docks
- Lake buoys and booms.
9/10/25 update: Newly received funding:
- $13,255.75 – Category A: Dumpster rentals
- $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility
- $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work
9/18/25 update: $2.8 million obligated for Flowering Bridge Demo: Version 0 - As noted above, Town officials will have to argue costs. The $2.8 million currently obligated represents a preliminary estimate, intended to provide the Town with initial funds to cover demolition costs already incurred and to support efforts to develop accurate replacement cost estimates. The Town is actively pursuing discussions with FEMA to negotiate a fixed cost offer based on the true cost of replacement. It is the Town’s intention that these valuable funds be directed toward priority recovery projects that will strengthen and restore our critical infrastructure. Read here for additional details.
10/31/25: There are no updates at this time.
|
Organization |
Funding Request |
Status |
|
State of NC-DEQ-Water (Loan with potential forgiveness) |
$3,000,000 |
Application under review |
|
FEMA-Revenue Replacement (Loan with potential forgiveness) |
Up to $5,000,000 |
Financial data under review; additional data being provided |
|
FEMA reimbursements |
Up to $7,500,000 |
5/2/25 Update: 5 projects now obligated for a total of $3,224,564.61. ·$862,186.69 Received 4/25 for a Category A (Debris Removal) 5/18/25 Update: $754,185.81 (anticipated 5/25) for a Category B (Emergency Protective Measures) (payment received) 5/23/25 Update: Received a check for $65,390.00 for Category A Town Wide Vegetative Debris Removal from ROW and Public Property. A new project was obligated for $118,323.67 for Category B Temporary Hydroelectric Plant Emergency Repairs. (payment received) 6/23/25 Update: Received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C); 8/4/25 Update: Received $8,250 for Temporary Town Hall Facility (Category B); Received $13,255.75 for Lake Lure Dumpster Rentals (Category A); 9/10/25 update: Newly received funding: $13,255.75 – Category A: Dumpster rentals; $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility; $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work |
|
DEQ-ARPA Reimbursement (non-storm related) |
Up to $3,000,00 |
Submission under review |
|
Private Donations |
Up to $90,000 |
Deposited; being held for future disbursement under discretion of Town Council |
|
Other Revenues and Payments from Insurance proceeds and claims |
Up to $5,000,000 |
50% has been approved for release 1/7/25 Update: 50% received. 1/31/25 Update: $1.3 million insurance payment for damage to Town Hall. |
|
NC Treasurer Cash Flow Loan |
$3,423,122.89 |
3/21/25 Update: Received 6/23/25: The Town was offered an additional $2.8 million in cash flow funds from the State Treasurer. A recommendation regarding this offer will be made to Town Council for consideration. 6/25/25: Town Council approved the loan. 7/29/25: Received a $2.8 million dollar loan disbursement this week from the NC Treasurer |
MONETARY DONATIONS
Our community, along with many of our neighbors, has been devastated by the catastrophic flooding caused by Hurricane Helene. The Town of Lake Lure, NC is deeply grateful for the support our community has received. We have had numerous requests to establish a mechanism for financial donations. Please click on the following link to donate to the Town of Lake Lure Storm Recovery Fund.
https://www.paypal.com/ncp/payment/WXB6HYYE8Y5PJ
Additional options for monetary donations include the following:
- Hickory Nut Gorge Outreach: https://hickorynutgorgeoutreach.org/one-time-donation/
- Hurricane Helene – Força Foundation: https://forcafoundation.com/hurricane-helene/
- RHI Legacy Foundation will match any donation up to $50,000 at www.rhilegacyfoundation.com
- Restore Lake Lure Fundraising Campaign: https://www.restorelakelure.com/ The Restore Lake Lure campaign seeks to bridge the gap between governmental support and personal sacrifice."
- The Foundation For Lake Lure/Chimney Rock Area Businesses: https://foundation4lakelurechimneyrock.com/home\
- United Way of Rutherford County at www.unitedwayofrutherford.org
STORM RECOVERY ACCOMPLISHMENTS
Swift evacuation by first responders saving countless lives 9/27/24.
Countless rescues first responders during and following Hurricane Helene.
Coordination with the Rutherford County Emergency Management during and throughout the storm.
Dam assessment and stabilization immediately following the storm event 9/27/24-9/29/24.
Communication with the Rutherford County EOC and FEMA for recovery immediately following the storm.
Coordination with volunteer groups to provide hot meals, shower services, restrooms, and handwashing stations in strategic locations by 10/1/24. Christian Aid Ministries served 8,080 hot meals and assisted 43 homeowners with clean-up of their homes and property. There were 164 volunteers and they spent 2,457 hours assisting our community!
Creation of donation stations to disseminate supplies throughout town by 10/1/24.
Cleared Highways and Town roads within days of the storm.
Restoration of water service throughout Town with water quality testing allowing Boil Advisory lifted 10/14/24 and 10/16/24 respectively.
Rapid repair of power services throughout Town by Duke Power and REMC.
Establishment of temporary communications systems through Starlink (10 systems) and Cell on Wheels with AT&T and Verizon 10/16/24.
Replacement of fiber to re-establish internet and cell service to the area 10/18/24.
Repair to the left abutment of the Dam by 10/27/24 with 2,494.64 tons of material securing the area.
Army Corps of Engineers contract signed with AshBritt to oversee lake debris and silt/sedimentation removal during a 160 day period of performance beginning 10/28/24. Debris removal began 11/4/24.
Emergency repairs to the sewer system completed, allowing "no flush order" to be lifted for most on 10/28/24.
Reopening of the Dam Bridge on Buffalo Shoals Road on 10/31/24.
Dittmer Watts Nature Trails and a portion of the Green Space reopened on 11/19/24.
Pressure Reducing Valve Construction in Lake Lure Town Center successfully completed 11/22/24.
The Boys Camp Road Temporary Bridge was completed 11/26/24.
As of 1/23/24, Over 32,782 CY of debris were removed from the right of way, 27,669 tons of sediment and silt have been removed from Town and the Parks, 24,558 cubic yards (CY) of debris have been removed from the Lake.
1/10/25: Burnt Ridge Landslide repair completed.
1/7/25: 50% of insurance payments received.
1/22/25: Contracted with lobbyist Hager Strategic Solutions (lobbyist).
1/22/25: Proclamation to open Chimney Rock State Park as soon as possible to bring in tourism to the area and strengthen the economy.
1/31/25: Culvert repair on Hummingbird Cove completed.
1/31/25: $1.3 million insurance payment received for damage to Town Hall.
2/11/25: Waste Water Treatment Plant is now operational. Repaired 3 water leaks throughout the water system
2/14/25: Storm drain box culvert repaired at corner of Memorial Hwy and Charlotte Dr
2/19/25: Youngs Mountain Trail landslide repaired
2/21/25: Green Space drainage repairs completed, grass replanted, and dry creek beds put into place.
2/28/25: The Town of Lake Lure and all those in areas code 28746 are eligible to apply for a free option for debris removal program through the USACE.
3/7/25: Debris removed from Morse Park trails and grass replanted in that area.
3/14/25: FEMA approval of the mission assignment for Lake Surface Debris, silt, and sedimentation removal through FEMA and the US Army Corps of Engineers.
3/18/25: Community Forum held with FEMA, USACE at The Lakeside Terrace with approximately 200 attendees.
3/18/25: United Way presented Fire Chief Dustin Waycaster a check for $50,000 for a new heart monitor for Firefights/AMTs.
3/27/25: Reservoir Drain Valve Installation complete.
4/24/25: 371 +/- boats that have been removed from the lake.
4/25/25: Reopened the East entrance to Morse Park.
5/2/25: $862,186.69 Received 4/25 for a Category A (Debris Removal)
5/11/25: $754,185.81 Received for a Category B (Emergency Protective Measures)
6/12/25: New seawall completed at the Lake Lure Gazebo
6/13/25: New pavers replaced broken and missing pavers in the Morse Park walkway and in front of the Lake Lure Beach.
6/17/25: The Lake Lure Beach was replenished with fresh sand.
6/23/25: The Town received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C)
6/25/25: Cash flow loan approved for $$2.8 million.
6/27/25: Downslide repaired on Angler's Way.
7/21/25: Repairs on Boys Camp Road completed.
7/21/25: Debris and silt/sedimentation removal from the Rumbling Bald Beach and Marina are complete.
7/28/25: Town Hall relocated to temporary office space in The Landings. The official opening date for the public is 8/1/25.
7/28/25: The Town received the $2.8 million loan disbursement this week from the NC Treasurer.
8/7/25: Received $8,250 from FEMA for Temporary Town Hall Facility (Category B); Received $13,255.75 from FEMA for Lake Lure Dumpster Rentals (Category A).
8/13/25: Silt/sedimentation removal began in Washburn Marina and coves around the lake, like Tryon Bay.
8/20/25: Asheville Tennis Association presented the Town of Lake Lure with a check for $19,000 to help rebuild our future tennis/pickleball courts.
8/20/25: The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.
8/20/25: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.
8/30/25: West end Sewer System largely restored.
9/10/25: FEMA funding received: $13,255.75 for Dumpster rentals, $28,531.78 for Temporary Relocation Costs – Town Hall Facility, $9,681.02 for Municipal Water Supply Damage
9/19/25: Proctor Road restoration project complete.
9/26/25: The Town received a total of $380,000 in a FEMA HHPD Grant for the Field Investigation Project that was recently completed.
9/27/25: Lake Lure and Chimney Rock came together to hold a one year Commemoration Ceremony
10/15/25: The new KaBOOM! Playground equipment was installed 10/13/25 - 10/15/25 through a grant from BCBS. Over 100 volunteers participated in the installation.
10/31/25: Partial completion of the West end connector allowing The 828, Hair Therapy, and those on Buddy Lane to connect to the water and sewer system.
ONGOING
- Emergency repairs to the sewer system.
- Constant removal of silt, sedimentation, and debris from the lake and roadways.
- Removal of condemned boathouses and personal property debris removal.
- Town officials are working to develop a comprehensive plan for future prosperity in the Town of Lake Lure.
WHAT’S OPEN IN THE TOWN OF LAKE LURE!

While visitors should be mindful of ongoing recovery efforts, several local businesses and recreation areas have reopened. There are a number of attractions that are open in the area. Lake Lure hotels, lodges, bed & breakfasts, and our amazing restaurants are open for business! Our local businesses greatly appreciate your patronage! Please visit the area and encourage others to visit as well.
Download the 2025 Travel Guide here.
Please visit the Local Restaurant Guide
Download the Falling Back in Love with Lake Lure and Chimney Rock Passport
And here are some of the amenities that are currently open to the public.
- Morse Park Walkway and the Lake Lure Gazebo (temporarily closed during silt removal in Marina Cove.)
- Dittmer-Watts Nature Trails
- Lake Lure Green Space
- Pool Creek Picnic Park
- Youngs Mountain
- Rumbling Bald Golf Courses
- Chimney Rock State Park – Rumbling Bald Access
- Chimney Rock State Park – Now open daily by reservation - Click here to reserve your tickets!
Additionally, horseback riding is available in the area along with zip lining, escape rooms, a candy cabin, and so much more!
Buffalo Creek Park/Weed Patch Mountain Trail/Upper Boulders Trail: Ongoing work is also taking place at Buffalo Creek Park, Weed Patch Mountain, and the Upper Boulder Trails by the National Guard, Carolina Climbers Coalition, Rutherford Outdoor Coalition, EcoForesters, and AmeriCorps. We cannot thank them enough for their time and support! Progress continues to be made on Upper Boulders Trail, and a small section may be opening soon. The Town will receive a grant of $50,000 to assist with restoration. Please stay tuned for updates!
Upcoming Events:
-
10/31/25 – 11/1/25: Lake Lure Classical Academy's Haunted Trail and Fall Festival (6-9 PM)
-
11/5/25: Comprehensive Planning Public Input Session at The Landings (4-7 PM)
-
11/11/25: Lake Lure Veterans Day Program on the Rumbling Bald Lakeview Terrance (9 AM)
- 12/3/25: Town Lighting Up Lake Lure Holiday Event at the Gazebo (5:30 PM)
QUESTIONS/SUGGESTIONS
You may review previous Storm Recovery Updates in Town News at www.townoflakelure.com
For questions or suggestions, please email Communications@townoflakelure.com

