Lake Lure Storm Recovery Updates and More - 9/5/25

9/2/25 Ground Breaking for Cell Tower

 

CONNECTING FOR THE FUTURE - BREAKING GROUND ON THE CELL TOWER

For those who have experienced challenges with phone service in Lake Lure - crews were finally able to break ground for the new cell tower! 

The location of the cell tower will be off Boys Camp Road on the old campground property. 

  • The site and access road grading began 9/2/25. 
  • Crews will begin construction 9/15/25.
  • The tower will be 195 feet tall and will have a sleek monopole design. 
  • The Federal Aviation Administration does not require a light at that height.
  • The cell tower is engineered to collapse in half in event of a pole failure.
  • The tower will be at least 120 feet from any property lines and will be fenced in with tree plantings around the fence for screening.
  • Tillman Infrastructure is building the tower and will own it.
  • They will lease antenna space to cellular service providers and AT&T will be the primary provider.
  • Verizon has leased the next highest space and T-Mobile will be the third provider.
  • Stay tuned for updates here.

 

LAKE RESTORATION

 

8/31/25 marked day 340 of the Hurricane Helene response and a major milestone at Lake Lure, where more than 1 million cubic yards of debris have been cleared from the lake.  

Watch the video here. 

https://www.facebook.com/reel/1734990557175912

Across western North Carolina, the U.S. Army Corps of Engineers have removed more than 6.4 million cubic yards of debris from waterways impacted by the hurricane.

HOW MUCH SILT AND DEBRIS HAVE BEEN REMOVED FROM LAKE LURE?  The US Army Corps of Engineers (USACE) has provided the following data on silt and debris removal from Lake Lure as of 8/31/25.

  • A total of 1,002,772 tons of silt/sediment have been removed from Lake Lure (29,012 tons in the last week).

  • A total of 98,780 98,288 cubic yards of debris has been removed from the waterway (492 cubic yards in the last week).

 

WHAT IS THE LAKE LEVEL? The Lake Level is at about 968 Mean Sea Level (MSL). (Full pond is 990.5 MSL) 

  • This is about 8 feet up from the lowest level so contractors can begin getting into the coves to remove silt and debris. 
  • The lake levels remain lower than it has ever been since the lake was built in the mid 1920's.  
  • The new reservoir drain (completed in April 2025) allowed Town staff to lower the lake beyond the limits of the Tainter gates, which are normally used to control the lake level. 
  • The lake level will remain drawn down at this stage of the lake restoration. 
  • The photo here shows the silt and debris removal in the Washburn Marina.

Silt and Debris Removal in Marina Cove 

HOW LONG WILL THE LAKE BE DOWN?  We are unable to specify the length of the drawdown period as this is dependent upon the sedimentation and debris removal process being overseen by the USACE

  • When a change in the lake level is planned, it will be posted here. 
  • As you can see from this photo below, work in the Washburn Marina area is going strong. 
  • You may watch the high-speed video of the silt removal process here.
  • Throughout the lake drawdown, Town engineers and staff will be scheduling work and inspections on the dam and the sewer system.

090225 silt removal Marina Cove

Dredging near the Lake Lure Beach and the Marina Cove 

WHY CAN'T WE ACCESS THE LAKE? The Town of Lake Lure and all businesses are open and welcoming visitors; however, the lake itself remains closed to all unauthorized personnel.  

  • Lake Lure is currently a Federal Work Site. 
  • Do not enter the lake or the lakebed for everyone's safety, and to avoid fines. 

 

WHERE DOES ALL THE SILT/DEBRIS GO?  The sand and the construction and demolition material are taken to the Republic Landfill in Union County, SC, out of an abundance of precaution.  

  • The vegetative material is taken to the area behind the Lake Lure Fire Department, where it is reduced. 
  • The mulch is hauled to a landfill in Canton, NC.  

 

HOW DO THEY KNOW WHERE DEBRIS IS LOCATED? The U.S. Army Corps of Engineers employed cutting-edge technology to revolutionize debris cleanup in western North Carolina. Drones equipped with cameras and LiDAR sensors help crews locate debris, verify loads, and speed up debris removal, all while maintaining the safety of recovery crews.

 

WHEN WILL THE LAKE REOPEN?   The lake restoration is a dynamic process so the date for reopening the lake is uncertain. 

  • We do not have a definitive timeline for completion at this time. 
  • The Town of Lake Lure remains hopeful that we will be able to reopen the lake in 2the late spring of 2026. 

 

BEYOND THE LAKE, HOW WAS THE TOWN IMPACTED BY HURRICANE HELENE? The impact to the Town of Lake Lure is unimaginable.

  • Unfortunately, Lake Lure’s nearly 100-year-old utilities infrastructure (sanitary sewer systems and wastewater treatment plant), our dam, Town Hall, Welcome Center, and municipal buildings, the Washburn Marina and floating boardwalk, the lake itself, and surrounding roadways and vehicular bridges were also significantly damaged by the devastating hurricane and flooding. 

  • Town officials have been working with FEMA, applying for grants, working with local and state representatives to obtain funding, and utilizing existing capital from the small Town's budget to restore these vital resources.  The Town cannot take action to restore or rebuild these buildings until FEMA makes the final determination and funding becomes available to address these facilities. 

 

HOW HAS THE WATER IN LAKE LURE BEEN IMPACTED? Please see the attached water sample results from June 30, 3035. 

  • All results are within normal limits, except for a very slight turbidity elevation near the debris site.
  • This is expected, with all the construction taking place.  
  • You may review the updated spreadsheet, which illustrates all the water sample data received by the Town of Lake Lure. 
  • For questions, please contact Communications@townoflakelure.com

 

MEETING THE MARK

 

The following is a summary of the high-level meetings from the past week.

  • Town Council Storm Recovery Meeting: Town Council met with Town leaders to discuss and move forward the ongoing work of the storm recovery.  Updates are included throughout this report.

  • FEMA Meeting:  Town Officials continue to meet with FEMA Officials to advance the complex public assistance projects. 

  • Administrative Staff Meeting: Town leaders and staff participated in a routine administrative meeting.

  • Media: Mayor Pritchett participated in an interview with the Post and Courier from Charleston, SC to discuss the storm recovery efforts in Lake Lure. 

  • Regional Planning Meeting: Mayor Pritchett participated in a meeting with County and State officials to discuss strategies to strengthen Lake Lure. 

  • Storm Recovery Meeting: Town leaders met to continue plans for recovery efforts in 2026. 

  • Morse Park Restoration: Town officials met to plan for the restoration of Morse Park once the silt and debris removal process is complete.
  • Sewer System Meeting: Town officials met with engineers from LaBella Associated for the ongoing work to restore and rebuild the town's sewer system and to seek funding to support this effort. 

  • ICF Meeting: Lake Lure Town Officials met with ICF officials to discuss the progress, status, and information required for FEMA reimbursements.
  • North Carolina Emergency Management (NCEM): Town officials participated in a meeting with MCEM for ongoing emergency preparations.
  • Environmental Protection Agency (EPA) Planning Meeting: Town officials participated in a meeting with EOPPA officials to plan a trip to Lake Lure in September to assess the storm recovery and to assess Town needs. 

  • NCDOT Dam Bridge: Town Officials participated in a meeting with NC DOT to discuss options for the bridge over the replacement dam that is being planned.

  • Media: Town officials facilitated filming an episode of the Wailing Earth docuseries at Buffalo Creek Park.  See other episodes at:  https://www.youtube.com/@TempleofSeaweed

    • ​​​​​​​What is the story that’s told in the wake of natural disaster? Over the past nine months, Temple of Seaweed, an Asheville-based production company, has worked to tell stories that convey the pain, grief, and enormous beauty of Western North Carolina in the aftermath of Hurricane Helene. 
    • What is the story that’s told in the wake of natural disaster? Over the past nine months, Temple of Seaweed, an Asheville-based production company, has worked to tell stories that convey the pain, grief, and enormous beauty of Western North Carolina in the aftermath of Hurricane Helene.
    • Geologist Brian Yanites noted, “Helene was a powerful reminder that natural hazards don’t disappear when the skies clear—they evolve.” So do the stories of the people in our community. WAILING EARTH has offered community members a compassionate platform to speak freely of acute trauma, to express the flood after the flood. The project has presented deeply moving narratives and many lessons on the slow, weathered shape of survival.  

 

Filming Wailing Earth in Buffalo Creek Park

 

IN THE NEWS

 

  • I Feared What Hurricane Helene Had Done to Our Community. One Year Later, We Have Hope 

    By Jacob Matthews

     It’s been almost a year since Hurricane Helene reshaped Western North Carolina and Southern Appalachia. But as a native of that region, I remember it like it was yesterday: the reports of catastrophic flooding, thousands of mudslides, and infrastructure failures—from interstate closures to cell towers being offline.  

    Four days after the storm, I had still not heard from my parents. Cell service across the region was down, power was still out, and there was no way in or out. They were stranded five hours away, and I had no idea if they were OK.  

    When I loaded up my truck with extra gas tanks, cases of water, food and toiletries, I had no idea if I was even going to make it home.  

    It was not until I had gotten to Raleigh that I heard I-26 had reopened for traffic into the region. Not 30 minutes later, for the first time in a week, I heard from my brother, who told me my family was safe.  

    But many families in our community weren’t so lucky. They lost everything, including their loved ones.  Read more here.

  • Governor Stein Provides His First NC Strong Update: Today Governor Josh Stein held the first NC Strong Update, updating the public on the progress the state has made to lead in artificial intelligence (AI), create jobs, achieve educational excellence in public schools, and ensure preparedness before natural disasters strike.  Read more here.
  • Hurricane Helene recovery funding restored for WNC after legal battle

    Saturday, August 30, 2025 9:25AM 

    ASHEVILLE, N.C. (WTVD) -- Approaching the one-year mark since Hurricane Helene struck, Western North Carolina is receiving much-needed recovery funding that was previously restored..

    In April, AmeriCorps ordered over 50 full-time volunteers to stop working on Helene recovery efforts in Western North Carolina. This decision was part of a broader termination of over 750 National Civilian Community Corps volunteers and more than $400 million in service programs nationwide.

    A few weeks later, North Carolina Attorney General Jeff Jackson joined a coalition of 22 other attorneys general in suing AmeriCorps for failing to administer already-approved grants. On Friday, he announced that the agency and the Office of Management and Budget had agreed to release all of the funds and distribute them as quickly as possible.

    Jackson spoke with Eyewitness News about the effort to restore those funds: "It was against the law. Congress had already approved this money, so it could not be defunded. We filed this lawsuit. We were fortunate the other party realized they were likely to lose in court, and they decided to fold and release all of the funds. We understand the funds will be distributed as soon as possible."

    The restored funding will support emergency response efforts for displaced individuals and those requiring various healthcare services. Programs such as Project MARS (Big Brother Big Sisters of WNC), Project Conserve, and Project POWER can now continue their work.

    "This money belongs to North Carolina and is crucial for western North Carolina's recovery. I'm deeply grateful for the AmeriCorps members on the ground who can keep helping our communities rebuild after Helene," Jackson said in a news release. Watch the newscast and read more here.

  • NC Gov. Stein reiterates call for more Helene relief money from Congress 

    NC Newsroom | By Adam Wagner

    Published September 3, 2025 at 4:42 PM EDT

    Dominick Gucciardo walks to his home in the aftermath of Hurricane Helene, Thursday, Oct. 3, 2024, in Pensacola, N.C.

    North Carolina's governor continued this week to call for Congress to provide for more money to help western North Carolina recover from last September's Helene.

    The storm drenched the mountainous region with heavy rains, leading to historic flooding and hundreds of landslides. In total, North Carolina officials estimate that Helene caused nearly $60 billion in damages.

    So far, the federal government has allocated about $5.24 billion to the state's recovery. That's not nearly enough, Gov. Josh Stein said at a press conference Tuesday.

    "My concern is whether this Congress and this administration is going to do a supplemental disaster appropriation, because that's where we need real money. We've had good money, but we need real money to help western North Carolina get back on its feet quicker," Stein said.

    In February, Stein requested an $11.6 billion relief package from Congress. Federal lawmakers have not taken action on that request so far.

    Stein and North Carolina recovery officials have pointed out recently that the federal government has funded about 6% of the estimated damages from Helene. They say that lags well behind other large hurricanes, including 2016's Hurricane Matthew and 2018's Hurricane Florence, where the federal government funded 53% and 20% of the damage, respectively.

    Stein also pointed to recovery funds for 2005's Hurricane Katrina, 2017's Hurricane Maria and 2012's Hurricane Sandy. In each case, the government provided funding totaling at least 73% of the estimated damages.

    "What we're asking for is not unreasonable. What we want is for the federal government to care about western North Carolina as they cared about Louisiana, as they cared about Puerto Rico, as they cared about New Jersey," Stein said.

         Read more here.

 

WATER AND SEWER SYSTEM 

 

West-end Sewer System: The work on the West End Sewer System Project began on 3/10/25 once easements were finally obtained by impacted property owners.  The West End Sewer System was destroyed by Hurricane Helene and was largely completed this week. The following properties impacted by the West End Sewer Project have restored sewer service:

Boys Camp Road properties: 109, 113, 160, 

Sea Wish Way: 114, 135, 137, 145, 186

Memorial Hwy: 3070, 3105, 3127, 3143, 3147

Town staff contacted property owners to inform them of the restoration. A few properties have laterals that run to the edge of our easement; those owners will need to work with a plumbing contractor to tie their service into the system.

For the remaining customers, the Town is awaiting the completed design for the line along Memorial Highway. All necessary materials are on hand and ready to be installed as soon as the design is received, aside from the manholes, which will be procured once the design is finalized.

Sewer Replacement Project: Town Officials met with LaBella Engineering to review current task orders and progress on the sewer replacement project. Upcoming phases for the sewer project were submitted to the NC Department of Environmental Quality (NC DEQ) for review in an Engineering Report/Environmental Information Document (ER/EID).  NCDEQ has provided initial comments and questions, which LaBella is actively addressing. In preparation for upcoming phases of the project, the Town has also begun communicating with several residents to discuss potential easement needs.

The Town continues to work closely with the North Carolina Division of Water Infrastructure (NC DWI) and neighboring communities to pursue a grant that will fund a study on the potential impacts and benefits of a regionalized sewer system.

Additionally, the Town is collaborating with NC DWI to secure supplemental State Revolving Fund (SRF) financing, which is expected to include principal forgiveness.

Sewer System Maintenance: Public Services continues to work to maintain the larger sewer system.  Planning and design work will be proceeding in Sunset Cove, Tryon Bay, Snug Harbor, and Grey Logs Cove in anticipation of future funding.  The Town has applied for FEMA funding to support restoration of the system.  We are awaiting a decision regarding this request and updates will be provided as new information becomes available.   

Mainline Sewer Repair: Public services officials have addressed an ongoing issue with a mainline sewer segment, implementing necessary repairs to improve service. 

Washburn Tank Cover Replacement: Successfully completed the replacement of 20 water tank system lid, improving system integrity and safety.

  • The Town has been working with LaBella Associates to design and replace the 20,000-gallon tank cover for the Washburn Tank.
  • The Authorization to Construct was issued on December 7, 2023, following the Water Tank Reconditioning Plan approval on November 7, 2023.
  • Although the project experienced delays due to Tropical Storm Helene, progress has continued.
  • The engineer’s certification was issued, and a request for final approval was submitted to NCDEQ on June 17, 2025.
  • Water testing was completed and yielded satisfactory results.
  • Final approval from NCDEQ was issued on July 11, 2025, officially marking the project's completion.

Lift Station: The system is operational and online

Waste Water Treatment Plant: The Waste Water Treatment Plant (WWTP) is operational, but we have submitted a request to FEMA for a replacement treatment system. We are awaiting a decision regarding this request and hope to relocate the system out of the flood zone.

LaBella Associates took these photos of the Lake Lure Pump Station before the hurricane, after the hurricane, and today after repairs. 

 

Lake Lure Pump Station behind the Lake Lure Dam before Hurricane Helene, after the storm, and today.

FEMA Public Assistance (PA) is working with the Town to move the permanent repairs for the Wastewater Treatment Plant (WWTP) forward as a Version 0 project, which allows the Town to receive funding for architectural and engineering (A&E) services.

  • A task order with LaBella was previously approved by Town Council, contingent upon FEMA funding.
  • Once this project is officially obligated, LaBella Associates will be able to proceed with the design work.
  • It is the Town's position—and that of the engineers at LaBella Associates, that the appropriate permanent repair for the WWTP is a full replacement of the facility, rather than piecemeal repairs to the existing plant, which is not feasible.

Utility Locate Responses: Responded to 26 utility locate requests through the 811 system, ensuring safe excavation and infrastructure protection across multiple work zones.

Are we applying for grants to assist with expenses? Yes!  LaBella Associates are working with Town officials to prepare an application for the Helene Recovery State Revolving Fund (SRF), which offers the potential for up to $5 million in principal forgiveness, if awarded. The SRF is a program that provides low-interest loans for water and wastewater infrastructure projects. 

Deep Water Ramp: The deep water ramp is being designed in the Rumbling Bald area. This will support various major infrastructure projects, but the primary focus is to support the sewer replacement project. 

 

PRIVATE WELLS

 

If you have a private well and lowering the lake has affected your well, then lake water may have been infiltrating your aquifer.

  • The first signs are sedimentation in your water, then air introduction to your system. 
  • The Town anticipates the lake will continue to be lowered for several more weeks. 
  • We do not currently have a date for refilling the lake as it is dependent upon the silt/sedimentation/debris removal being overseen by the USACE.  
  • It is recommended that individuals experiencing these indicators consult a well company.
  • Sedimentation can be filtered, but air usually means you need to dig a deeper well to retrieve water from a protected aquifer below the clay or rock layer.

The Town of Lake Lure consulted with the North Carolina Department of Environmental Quality regarding this matter to see if they could be of any assistance.  They provided the following link for individuals seeking financial assistance with their wells: Water Well Trust.  You may learn more about applying for this assistance here.

Additionally, here are resources for assistance with testing and disinfecting personal wells.

1)  Foothills Health District: Please click on the following link for Emergency Drinking Water Well Disinfection Procedures

     http://www.foothillshd.org/images/forms/4000/4001/FoothillsHealth_WellWa...

2)  Broad River Water Authority: 828-286-0640  https://www.ncbrwa.com/

3)  James & James Environmental Management, Inc.: 828-697-0063 https://www.facebook.com/jamesandjames1992/

 

KEEP IT IN THE ROAD!

 

Memorial Highway (64/74) between Lake Lure and Chimney Rock is open.

Highway 64/74A Beyond Chimney Rock Village: Highway 64/74A heading West beyond Chimney Rock Village remains closed to the public at large. It is open to "locals", which is defined as those who live and work in the area. Please do not use this road if you do not have to, as contractors have to stop their work to allow for passage when cars go by, slowing the recovery process. 

NC DOT updates on Highway 64: A temporary road is expected to be open between Chimney Rock and Hendersonville was extended to June 30, 2027 (YES, 2027). For more information, visit NC DOT’s Drive NC link: https://drivenc.gov/?type=incident&id=715074      

Update from Gerton Fire and Rescue: "We would like to impress that these roads are for local traffic only. We have had a surge in tourists over the last few weeks. Please stay out of the gorge if you do not live there and let them work." Gerton Fire Chief.

Proctor Road: The normal working hours for the project is from 7 AM till 5 PM Monday through Friday.  Proctor Road will be open and passable before 7:30AM, between 12:00-12:30, and after 5:00 PM Monday through Friday, and all day on Saturdays and Sundays. If there is an emergency situation, all equipment will be moved immediately for safe egress/ingress. Update 8/7/25: The timeline for project completion is estimated to be the 2nd week of September (depending on the weather).  

Lago Vista Road Extension: Town officials collaborated with Odom Engineering to solicit and review bids for the extension of Lago Vista Road, aimed at improving access to Chimney Rock State Park. The Town is currently working with state agencies to explore partnership opportunities to support the project.

 

PREPARATION FOR FUTURE HURRICANES

 

Rutherford County Emergency Management conducted siren testing in Lake Lure last week.  We are pleased to report that the sirens which were installed just before Hurricane Helene are all in good working order.

 

MORSE PARK TEMPORARILY CLOSED

 

To ensure the work can be completed safely and on schedule, Morse Park will be temporarily closed. 

  • We cannot provide a timeline for this project at this time, but weekly updates will be provided here.
  • The Town of Lake Lure understands the importance of Morse Park to our community, and we appreciate your patience during this temporary closure.
  • The Washburn Marina debris and sedimentation removal project is a critical component of our lake restoration, and completing it safely and efficiently will benefit everyone in the long run.
  • Port-a-potties have been relocated to Pool Creek beside the Arcade building.

While Morse Park is temporarily closed, the following areas remain open for public use:

These amenities are in Lake Lure and are open to the public.

We sincerely apologize for any inconvenience and thank you for your cooperation and support as we work toward reopening the lake. For questions, please email Communications@townoflakelure.com.

 

DAM UPDATES

 

  • Reservoir Drain: The reservoir drain project at the dam has allowed the Town to lower the lake to 30 feet as planned for the ongoing lake restoration work.  The drain is closed at times if work is taking place behind the dam to ensure safety.  Otherwise, it is open to allow a flow of water in the river. 

  • Field Testing for Replacement Dam: Schnabel Engineering is overseeing a geotechnical subsurface investigation to support the design of the replacement dam at Lake Lure. 

    • Task 1 – Investigation Planning – Complete
    • Task 2 – Field Investigations
    • Geologic Mapping: Complete.
  • Surface Geophysics: Complete.
  • Down-hole Geophysics: Geophysical surveys performed in 14 borings to date. Geophysical surveys planned for four additional borings.
  • Geotechnical Drilling and Sampling: 16 borings have been drilled to date (14 have been backfilled, and two left open for geophysical testing). Field staff have been on site to oversee drilling operations, log subsurface conditions, and collect soil and rock samples for laboratory   testing. Drilling for the last two borings began on July 21, 2025.
  • Surveying: Boundary, site feature, and topographic data collection is complete. The remaining survey work includes locating the two remaining borings to be drilled. We have received a draft survey deliverable and are currently reviewing the content.
    • Task 3 - Laboratory Testing: Completed laboratory testing on rock samples collected from the first 14 borings. An additional round of laboratory testing will be completed once the final two borings are completed. Completed laboratory testing on soil samples collected from the completed borings to evaluate their engineering properties.
    • Task 4 – Geotechnical Data Report and Design Considerations Memorandum: Have begun efforts on the Geotechnical Data Report (GDR). Reviewed all data collected to date (boring log data, geophysical data, laboratory data, etc.) for inclusion in the GDR. Once the GDR is complete, we will use the findings to prepare a Design Considerations Memorandum.
  • Tainter Gate Repairs: Schnabel Engineering conducted an inspection of the Tainter gates. Based on their findings, the Town Council approved a work order for the design of necessary repairs, including seal repair.  We anticipate this work being completed when lake levels come back up, potentially this winter. Schnabel Engineering is developing the scope of work, which includes the design of repairs to the dam’s concrete ogee (allows for uncontrolled flow over the top of the reservoir) and the installation of new rubber seals along the base of the Tainter gates. This project will be completed when the lake comes back up a bit, in the winter of 2025-26.

  • Grant to Support Design for Replacement Dam: We hope to begin design work for the replacement dam in the fall of 2025. We are hoping to receive confirmation on a FEMA High Hazard Dam Grant to support the cost of this project. We should receive a confirmation on this funding in September when the Field Testing work is complete. 

  • Boom: Schnabel is designing a boom for the dam area.

  • River Restoration: Successfully completed the restoration of the river channel located below the dam, returning it to its pre-storm condition. This project was executed entirely by Town personnel utilizing rented equipment, resulting in substantial cost savings compared to the use of contracted services. In addition to restoring hydraulic function and stability to the area, this work enabled the timely resumption of vital coring operations at the dam.

  • Recognition: We are also proud to share that the Town has been selected to receive the 2025 Southeast Regional Dam Safety Award from the Association of State Dam Safety Officials (ASDSO). This recognition highlights the Town’s efforts on the Low-Level Outlet Project, its proactive response to Hurricane Helene, and its ongoing commitment to securing funding for a long-term dam solution.

 

LAND BASED DEBRIS

 

Personal Property Debris Removal Video

Watch the process in action.

  • Private Property Debris Removal Work Underway in Lake Lure (Zip Code 28746): Private Property Debris Removal (PPDR) operations are wrapping up in Lake Lure, with crews finalizing the debris removal efforts in the area.
    • This mission led by the U.S. Army Corps of Engineers (USACE) in partnership with TEYA and AshBritt through a mentor-protégé agreement.
    • Approximately 10 to 12 crews are working daily from 7:00 a.m. to 7:30 p.m., with the goal of completing all debris removal, cleanup, and disposal within 30 days.
    • Crews are staging the debris at the space behind the Lake Lure Fire Department and then it will be transported to Enoree, South Carolina.
    • Only properties previously enrolled in the PPDR program are eligible for these services.
    • While this Direct Federal Assistance program is now closed to new applicants, residents may still register for the State’s Mission Assigned Recovery Taskforce (SMART) program.
    • For questions or concerns, residents are encouraged to contact ppdr@teyacompany.com.

       We appreciate the community’s continued patience and cooperation as we work together to restore and rebuild safely.

  • PPDR in Action: The U.S. Army Corps of Engineers and its contractors are hard at work in western North Carolina, clearing debris left in the wake of Hurricane Helene. USACE, tasked by FEMA, is on the ground supporting Personal Property Debris Removal, clearing fallen trees from private property. Each load removed means safer homes, clearer access, and one more step toward recovery.

Watch the process in action in this video. Each cleared site is a step closer to recovery.

 

LAKEFRONT DEBRIS

 

If you are a lakefront property owner, this photo illustrates a situation you might face with your lakeside debris. As you can see  the photo, the debris that has been collected near the dock is too far away from the excavator to remove it at the current lake level.  The US Army Corps of Engineers contractors have confirmed that they plan on removing debris in this general location when the water comes back up. In other words, they will be making another round to pick up debris once the water level is raised in the coming weeks. We do not have a date for raising the lake levels at this time, but this information will be posted on the town website when we have a timeline.

Barge Removing Debris and Silt

 

CONTRACTOR INFORMATION

 

Only approved contractors may access properties from the lake, by boat or barge, but any contractor or property owner may work on lake structures (with permits) if accessing from land.  This includes sea wall construction or restoration (again, with required permits).   You may emailkmartin@townoflakelure.com"> kmartin@townoflakelure.com with any questions.

Click here for additional information on contractors.

 

DAMAGED LAKE STRUCTURES

 

The Community Development Department has created a map showing most of the seriously damaged lake structures, over 100 boathouses.  These are properties that the owners agree to the demo of the boathouse. If you have damages, be aware that you will need to contact the Community Development Department about permitting for repairs or replacement.  Permits are being issued and work is being done on lake structures now, but all work must be authorized. 

  • For property owners who signed up for the no-cost demolitions by the Army Corp, they are working on their plan now and we will notify you as we have more specific timing information. 
  • We have confirmed that, if you are signed up for the condemnation/removal program, they will be contacting you individually for a “right of entry” agreement prior to beginning the work.
  • Town officials are working with the USACE to determine their timeline for this process, likely in the winter months. 
  • Please contact Community Development Staff for more information about the Army Corp program, as well as your permitting, at kmartin@townoflakelure.com or 828-625-9983, x 135.

 

FINANCIAL SUPPORT/APPLICATIONS

 

The following chart illustrates the financial support the Town of Lake Lure is currently seeking, in addition to Federal and State Funding requests that have been made on behalf of the Town through our political representatives (disaster management planning experts) and Hager Strategic Solutions (lobbyist).  They are assisting the Town with post-disaster federal funding applications and requests to expedite our recovery process.

There are now 34 projects that have been submitted to FEMA for consideration of funding and the Town is awaiting their review and feedback.

8/13/25 update: Nine FEMA-funded projects have been obligated. The Town has received $2,325,171.92 for seven of these, and two additional reimbursements totaling $38,212.80 are pending. Delays persist for projects over $100,000, and staff have begun contacting elected officials to address these concerns. 

8/20/25 update: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.

Several other projects are currently under review by FEMA. While the process continues to move slowly, we are seeing progress, and these projects are inching closer to obligation.

  • Diving Operations at the Dam ($700K range)
  • Flowering Bridge Demo: Version 0 - will have to argue costs. 
  • Community Center/Welcome Center: Came back at $160,000, which is far too low.
  • Marina Docks
  • Lake buoys and booms.

Organization

Funding Request

Status

State of NC-DEQ-Water

(Loan with potential forgiveness)

$3,000,000

Application under review

FEMA-Revenue Replacement

(Loan with potential forgiveness)

Up to $5,000,000

Financial data under review; additional data being provided

FEMA reimbursements

Up to $7,500,000

5/2/25 Update: 5 projects now obligated for a total of $3,224,564.61.

·$862,186.69 Received 4/25 for a Category A (Debris Removal)

5/18/25 Update: $754,185.81 (anticipated 5/25) for a Category B (Emergency Protective Measures) (payment received)

5/23/25 Update: Received a check for $65,390.00 for Category A Town Wide Vegetative Debris Removal from ROW and Public Property.

A new project was obligated for $118,323.67 for Category B Temporary Hydroelectric Plant Emergency Repairs. (payment received)

6/23/25 Update: Received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C); 

8/4/25 Update: Received $8,250 for Temporary Town Hall Facility (Category B);  Received $13,255.75 for Lake Lure Dumpster Rentals (Category A);

DEQ-ARPA Reimbursement (non-storm related)

Up to $3,000,00

Submission under review

Private Donations

Up to $90,000

Deposited; being held for future disbursement under discretion of Town Council

Other Revenues and Payments from Insurance proceeds and claims

Up to $5,000,000

50% has been approved for release

1/7/25 Update: 50% received.

1/31/25 Update: $1.3 million insurance payment for damage to Town Hall. 

NC Treasurer Cash Flow Loan

$3,423,122.89

3/21/25 Update: Received   

6/23/25: The Town was offered an additional $2.8 million in cash flow funds from the State Treasurer.  A recommendation regarding this offer will be made to Town Council for consideration.

6/25/25: Town Council approved the loan.

7/29/25: Received a $2.8 million dollar loan disbursement this week from the NC Treasurer

 

MONETARY DONATIONS

 

Our community, along with many of our neighbors, has been devastated by the catastrophic flooding caused by Hurricane Helene. The Town of Lake Lure, NC is deeply grateful for the support our community has received.  We have had numerous requests to establish a mechanism for financial donations. Please click on the following link to donate to the Town of Lake Lure Storm Recovery Fund.  

https://www.paypal.com/ncp/payment/WXB6HYYE8Y5PJ

Additional options for monetary donations include the following: 

 

STORM RECOVERY ACCOMPLISHMENTS

 

Swift evacuation by first responders saving countless lives 9/27/24.

Countless rescues first responders during and following Hurricane Helene.

Coordination with the Rutherford County Emergency Management during and throughout the storm.

Dam assessment and stabilization immediately following the storm event 9/27/24-9/29/24.

Communication with the Rutherford County EOC and FEMA for recovery immediately following the storm.

Coordination with volunteer groups to provide hot meals, shower services, restrooms, and handwashing stations in strategic locations by 10/1/24. Christian Aid Ministries served 8,080 hot meals and assisted 43 homeowners with clean-up of their homes and property.  There were 164 volunteers and they spent 2,457 hours assisting our community!

Creation of donation stations to disseminate supplies throughout town by 10/1/24. 

Cleared Highways and Town roads within days of the storm.

Restoration of water service throughout Town with water quality testing allowing Boil Advisory lifted 10/14/24 and 10/16/24 respectively.

Rapid repair of power services throughout Town by Duke Power and REMC.  

Establishment of temporary communications systems through Starlink (10 systems) and Cell on Wheels with AT&T and Verizon 10/16/24.

Replacement of fiber to re-establish internet and cell service to the area 10/18/24. 

Repair to the left abutment of the Dam by 10/27/24 with 2,494.64 tons of material securing the area.

Army Corps of Engineers contract signed with AshBritt to oversee lake debris and silt/sedimentation removal during a 160 day period of performance beginning 10/28/24.  Debris removal began 11/4/24.

Emergency repairs to the sewer system completed, allowing "no flush order" to be lifted for most on 10/28/24.

Reopening of the Dam Bridge on Buffalo Shoals Road on 10/31/24.

Dittmer Watts Nature Trails and a portion of the Green Space reopened on 11/19/24.

Pressure Reducing Valve Construction in Lake Lure Town Center successfully completed 11/22/24.

The Boys Camp Road Temporary Bridge was completed 11/26/24.

As of 1/23/24, Over 32,782 CY of debris were removed from the right of way, 27,669 tons of sediment and silt have been removed from Town and the Parks, 24,558 cubic yards (CY) of debris have been removed from the Lake.

1/10/25: Burnt Ridge Landslide repair completed.

1/7/25: 50% of insurance payments received.

1/22/25: Contracted with lobbyist Hager Strategic Solutions (lobbyist). 

1/22/25: Proclamation to open Chimney Rock State Park as soon as possible to bring in tourism to the area and strengthen the economy.

1/31/25: Culvert repair on Hummingbird Cove completed.

1/31/25: $1.3 million insurance payment received for damage to Town Hall. 

2/11/25: Waste Water Treatment Plant is now operational.  Repaired 3 water leaks throughout the water system

2/14/25: Storm drain box culvert repaired at corner of Memorial Hwy and Charlotte Dr

2/19/25: Youngs Mountain Trail landslide repaired

2/21/25: Green Space drainage repairs completed, grass replanted, and dry creek beds put into place.

2/28/25: The Town of Lake Lure and all those in areas code 28746 are eligible to apply for a free option for debris removal program through the USACE.

3/7/25: Debris removed from Morse Park trails and grass replanted in that area.

3/14/25: FEMA approval of the mission assignment for Lake Surface Debris, silt, and sedimentation removal through FEMA and the US Army Corps of Engineers.

3/18/25: Community Forum held with FEMA, USACE at The Lakeside Terrace with approximately 200 attendees.

3/18/25: United Way presented Fire Chief Dustin Waycaster a check for $50,000 for a new heart monitor for Firefights/AMTs.

3/27/25: Reservoir Drain Valve Installation complete.

4/24/25: 371 +/- boats that have been removed from the lake.

4/25/25: Reopened the East entrance to Morse Park.

5/2/25: $862,186.69 Received 4/25 for a Category A (Debris Removal)

5/11/25: $754,185.81 Received for a Category B (Emergency Protective Measures)

6/12/25: New seawall completed at the Lake Lure Gazebo

6/13/25: New pavers replaced broken and missing pavers in the Morse Park walkway and in front of the Lake Lure Beach. 

6/17/25: The Lake Lure Beach was replenished with fresh sand.  

6/23/25:  The Town received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C)

6/25/25: Cash flow loan approved for $$2.8 million.

6/27/25: Downslide repaired on Angler's Way. 

7/21/25: Repairs on Boys Camp Road completed.

7/21/25: Debris and silt/sedimentation removal from the Rumbling Bald Beach and Marina are complete.

7/28/25: Town Hall relocated to temporary office space in The Landings. The official opening date for the public is 8/1/25.

7/28/25: The Town received the $2.8 million loan disbursement this week from the NC Treasurer.

8/7/25:  Received $8,250 from FEMA for Temporary Town Hall Facility (Category B);  Received $13,255.75 from FEMA for Lake Lure Dumpster Rentals (Category A).

8/13/25: Silt/sedimentation removal began in Washburn Marina and coves around the lake, like Tryon Bay.

8/20/25: Asheville Tennis Association presented the Town of Lake Lure with a check for $19,000 to help rebuild our future tennis/pickleball courts.

8/20/25: The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.

8/30/25: West end Sewer System largely restored. 

ONGOING

  • Emergency repairs to the sewer system.
  • Constant removal of silt, sedimentation, and debris from the lake and roadways.
  • Removal of condemned boathouses and personal property debris removal.
  • Town officials are working to develop a comprehensive plan for future prosperity in the Town of Lake Lure.   

 

WHAT’S OPEN IN THE TOWN OF LAKE LURE!

 

Welcome to Lake Lure

Lake Lure Welcomes Visitors Back As Recovery Continues: While visitors should be mindful of ongoing recovery efforts, several local businesses and recreation areas have reopened.  There are a number of attractions that are open in the area. Lake Lure hotels, lodges, bed & breakfasts, and our amazing restaurants are open for business!  Our local businesses greatly appreciate your patronage!  Please visit the area and encourage others to visit as well. 

Download the 2025 Travel Guide here.  

Please visit the Local Restaurant Guide

And here are some of the amenities that are currently open to the public.  

  • Morse Park Walkway and the Lake Lure Gazebo (temporarily closed during silt removal in Marina Cove.)
  • Dittmer-Watts Nature Trails
  • Lake Lure Green Space
  • Pool Creek Picnic Park
  • Youngs Mountain
  • Rumbling Bald Golf Courses
  • Chimney Rock State Park – Rumbling Bald Access
  • Chimney Rock State Park – Now open daily by reservation - Click here to reserve your tickets!

Additionally, horseback riding is available in the area along with zip lining, escape rooms, a candy cabin, and so much more!

New Playground Planned: The Town has been approved for a grant for a replacement playground, which will be placed in Morse Park in October, just inside the walkway to the Gazebo.  October 13-15, 2025 will be volunteer prep and building days. Please join us!   

Buffalo Creek Park/Weed Patch Mountain Trail/Upper Boulders Trail: Ongoing work is also taking place at Buffalo Creek Park, Weed Patch Mountain, and the Upper Boulder Trails by the National Guard, Carolina Climbers Coalition, Rutherford Outdoor Coalition, EcoForesters, and AmeriCorps. We cannot thank them enough for their time and support!  Update 6/17/25: Progress continues to be made on Upper Boulders Trail, and a small section may be opening soon. The Town will receive a grant of $50,000 to assist with restoration.  Please stay tuned for updates!

Upcoming Events:

  • 9/27/25: The Town of Lake Lure is planning a special ceremony commemorating Hurricane Helene at 11:00 at the Morse Park Gazebo.  The event will honor those who lost so much during the flood while recognizing the resiliency of the Lake Lure Community and the tremendous recovery that has taken place.   Please join us!

  • 10/5-11/25: Cycle NC  Mountain is Coast ride, starting In Lake Lure

  • 10-13-15: KaBOOM Playground Building Project in Morse Park

  • 10/18-19/25: Hickory Nut Gorge Outreach Fall Arts and Crafts Festival

  • 10/18/25: Lake Lure Artist's Show and Sale

  • November 2025: Reopening Celebration and Ribbon Cutting for Buffalo Creek Park. Date to be determined.

 

TEMPORARY TOWN HALL

 

The Landings is the new temporary office space for Town Hall and the Police Department.

  • The Town Council approved a month-to-month lease agreement with The Landings to support continued operations while the Town and FEMA work together to identify a permanent solution for the damaged municipal facilities.
  • Starting in August, all Town Council and advisory board meetings—with the exception of the Lake Advisory Board (LAB) and the Parks and Recreation Board—will also be held at this new location.
  • LAB and Parks and Recreation Board meetings will continue to be held at the Parks, Recreation, and Lake Offices.
  • Lake Lure's Town Hall building at 2948 was flooded during Hurricane Helene.  The status of the building itself is uncertain at this time, as the Town is awaiting FEMA's determination on the facility and any funding.

 

COMPREHENSIVE PLAN

 

The Town has officially initiated the Comprehensive Plan process. To help guide this important effort, an 11-member steering committee has been established. In addition to advising on the overall process, committee members will help promote community engagement, review draft materials, and serve as a vital connection between the public, planning staff, and Town leadership.

  • The steering committee will begin meeting prior to the public input phase.
  • These early meetings will help establish the framework and key themes to ensure that public engagement is inclusive, focused, and productive.
  • The public will have multiple opportunities to participate in shaping the plan, including through surveys, community input sessions, and town hall meetings—anticipated to begin in October.

 

QUESTIONS/SUGGESTIONS

You may review previous Storm Recovery Updates in Town News at www.townoflakelure.com

For questions or suggestions, please email Communications@townoflakelure.com