Lake Lure Storm Recovery Updates and More - 9/20/25

Lake Lure Aerial view

 

The US Army Corps of Engineers continues their work in Lake Lure, where more than one million cubic yards of debris has been cleared. Crews have completed 96 percent of subsurface removal with anticipation of completion of debris removal at the lake by the end of October.  The lake is looking beautiful as you can see from this aerial shot by Lake Lure Marine. Each milestone brings communities a step closer to recovery.

Watch the video here. 

USACE Silt Removal Lake Lure
 

HOW MUCH SILT AND DEBRIS HAVE BEEN REMOVED FROM LAKE LURE?  

 

The US Army Corps of Engineers (USACE) and their contractors have provided the following data on silt and debris removal from Lake Lure as of 9/14/25.

  • A total of 1,110,881 tons of sand/silt and sediment have been removed from Lake Lure. 

  • A total of 99,567 cubic yards of debris has been removed from the waterway 

 

WHAT IS THE LAKE LEVEL? 

 

The Lake Level is at about 968 Mean Sea Level (MSL). (Full pond is 990.5 MSL) 

  • This is about 8 feet up from the lowest level so contractors can begin getting into the coves to remove silt and debris. 
  • The lake levels remain lower than it has ever been since the lake was built in the mid 1920's.  
  • The new reservoir drain (completed in April 2025) allowed Town staff to lower the lake beyond the limits of the Tainter gates, which are normally used to control the lake level between 1-12 feet below full pond. 
  • The lake level will remain drawn down at this stage of the lake restoration. 
  • The photo here shows the silt and debris removal in the Washburn Marina this past week.

Marina Silt Removal

Silt and Debris Removal in Marina Cove 

 

HOW LONG WILL THE LAKE BE DOWN?  We are unable to specify the length of the drawdown period as this is dependent upon the sedimentation and debris removal process being overseen by the USACE

  • When a change in the lake level is planned, it will be posted here. 
  • As you can see from this photo above, work in the Washburn Marina area is going strong. 
  • Throughout the lake drawdown, Town engineers and staff will be scheduling work and inspections on the dam and the sewer system.

 

WHY CAN'T WE ACCESS THE LAKE? The Town of Lake Lure and all businesses are open and welcoming visitors; however, the lake itself remains closed to all unauthorized personnel.  

  • Lake Lure is currently a Federal Work Site. 
  • Do not enter the lake or the lakebed for everyone's safety, and to avoid fines. 

 

WHERE DOES ALL THE SILT/DEBRIS GO? 

 

The sand and the construction and demolition material are taken to the Republic Landfill in Union County, SC, out of an abundance of precaution.  

  • The vegetative material is taken to the area behind the Lake Lure Fire Department, where it is reduced. 
  • The mulch is hauled to a landfill in Canton, NC.  

 

WHEN WILL THE LAKE REOPEN?   

 

The lake restoration is a dynamic process so the date for reopening the lake is uncertain. 

 

LAKE LURE WATER QUALITY

 

HOW HAS THE WATER IN LAKE LURE BEEN IMPACTED? Please see the attached water sample results from July 28, 2025. 

  • All results are within normal limits, except for a very slight turbidity elevation near the debris site.
  • This is expected, with all the construction taking place.  
  • You may review the updated spreadsheet, which illustrates all the water sample data received by the Town of Lake Lure. 
  • For questions, please contact Communications@townoflakelure.com

 

BEYOND THE LAKE, HOW WAS THE TOWN IMPACTED BY HURRICANE HELENE? 

 

The impact to the Town of Lake Lure is unimaginable.

  • Unfortunately, Lake Lure’s nearly 100-year-old utilities infrastructure (sanitary sewer systems and wastewater treatment plant), our dam, Town Hall, Welcome Center, and municipal buildings, the Washburn Marina and floating boardwalk, the lake itself, and surrounding roadways and vehicular bridges were also significantly damaged by the devastating hurricane and flooding. 

  • Town officials have been working with FEMA, applying for grants, working with local and state representatives to obtain funding, and utilizing existing capital from the small Town's budget to restore these vital resources.  The Town cannot take action to restore or rebuild these buildings until FEMA makes the final determination and funding becomes available to address these facilities. 

 

MEETING THE MARK

 

The following is a summary of the high-level meetings from the past two weeks.

  • Town Council Storm Recovery Meeting: Town Council met with Town leaders to discuss and move forward the ongoing work of the storm recovery.  Updates are included throughout this report.

  • Media: Mayor Pritchett participated in an interview with WCNC Charotte on the one year anniversary of Hurricane Helene. This news spot will air near the anniversary date 9/27/25. 

  • Playground Planning Meeting: Town officials met with KaBoom representatives to plan for the new playground equipment. Volunteers are needed to support the effort.

lake_lure_build_week_flyer

  • Marine Commission Meeting and Public Hearing: The Marine Commission met 9/9/25.  The Lake Use Regulations were updated.  You may download a summary of the meeting here.

  • Town Council Meeting and Public Hearing: Town Council held a regular meting and public hearing on 9/9/25.  Updates are included throughout this report. You may download a summary of the meeting here.

  • Environmental Protection Agency (EPA) Planning Meeting: Town Officials met with EPA representatives to plan for their visit to Lake Lure on 9/17/25.

  • FEMA Meeting:  Town Officials continue to meet with FEMA Officials to advance the complex public assistance projects. 

  • ICF Meeting: Lake Lure Town Officials met with ICF officials to discuss the progress, status, and information required for FEMA reimbursements.

  • Duke Energy Meeting: Lake Lure Town Officials met with Duke Energy representatives to discuss ongoing projects.

  • Governmental Accounting and Financial Reporting: Town Officials particioated in a Governmental Accounting and Financial Reporting meeting in Asheville.

  • North Carolina League of Municipalities (NCLM) Meeting: Town Officials met with NCLM representatives for an inspection of the Lake Lure Welcome Center. 

  • Sewer System Meeting: Town Officials met with engineers from LaBella Engineering for ongoing discussions and planning for maintenance of the exiting sytem and planning for the replacement system. 

  • Staff Administrative Training Meeting: Town staff participated in Microsoft 365 training. 

  • Media: Mayor Pritchett participated in an interview with Blue Ridge Public Public Radio’s reporter, Katie Myers to discuss the storm recovery efforts in Lake Lure. 

  • EPA Visit: Regional EPA Representatives visited Lake Lure to see the progress that has been made in the past year since Hurricane Helene.  Officials toured the Dam, the Syewer System and Morse Park.  They held a press conference to share their fndings.   

091725 EPA Visit - Tour of Dam

 

  • Media: Mayor Pritchett participated in a taped panel discussion with Carolina Business Review on the storm recovery efforts underway in Lake Lure. 

  • Storm Recovery Meeting: Town leaders met to continue plans for recovery efforts in 2026. 

  • NC Department of Environmental Quality - Division of Water (DEQ DWI) Meeting: Town Officials met with DEQ DWI) for ongoing discussions and planning for maintenance of the exiting sewer sytem and development and funding for the replacement system.

 

 IN THE NEWS

 

1. NC leaders push for faster FEMA aid in D.C., millions in approved funds remain unpaid. By Kimberly King

Watch the newscast

1. WLOS NC leaders push for faster FEMA aid in D.C., millions in approved funds remain unpaid

SEPT. 17, 2025 - Asheville Mayor Esther Manheimer, Lake Lure Mayor Carol Pritchett and leaders from Haywood County, Madison County and Waynesville stood at the capital in D.C. on Wednesday after meeting with FEMA officials and North Carolina’s Congressional and Senate delegations, including Senator Ted Budd and Congressman Chuck Edwards. North Carolina Governor Josh Stein was also in D.C. as part of the delegation. (Photo courtesy: American Flood Coalition)

ASHEVILLE, N.C. (WLOS) — Asheville Mayor Esther Manheimer, Lake Lure Mayor Carol Pritchett and leaders from Haywood County, Madison County and Waynesville stood at the capital in D.C. on Wednesday after meeting with FEMA officials and North Carolina’s Congressional and Senate delegations, including Senator Ted Budd and Congressman Chuck Edwards.

North Carolina Governor Josh Stein was also in D.C. as part of the delegation. The trip of local leaders was launched by the American Flood Coalition and its support for leaders to advocate for flood aid and flood prevention infrastructure after Helene.

$575K FEMA-APPROVED REIMBURSEMENT PART OF DOGE REVIEW PROCESS: NC EMERGENCY MANAGEMENT

Budd has been advocating for faster delivery of Federal Emergency Management Agency funds and federal aid dollars.

Read more here. 

FEMA Meeting in DC wth Mayor Carol Pritchett

$575K FEMA-APPROVED REIMBURSEMENT PART OF DOGE REVIEW PROCESS: NC EMERGENCY MANAGEMENT

Budd has been advocating for faster delivery of Federal Emergency Management Agency funds and federal aid dollars.

News 13 reviewed the 257 FEMA-approved projects approved since August. The spreadsheet compiled by Budd’s staff shows various projects, including tens of millions in federal reimbursements for NCDOT, FEMA-approved funds for Asheville, and $745,485 for Lake Lure dam repairs.

2. EPA highlights Western North Carolina recovery efforts nearly a year after Helene

Watch the newscast. 

EPA Highlights Western NC recovery efforts nearly a year after Helene

 

The Environmental Protection Agency joined state and local officials at multiple locations across western North Carolina on Wednesday to showcase recovery work completed over the past year and highlight ongoing rebuilding efforts in the region after Hurricane Helene. EPA officials joined local leaders at several landmarks, including the Lake Lure Dam and Morse Park, to reflect on the recovery that’s been made and the work still left to do. “Seeing what our staff, as well as the other agencies we've been working with, have been able to accomplish in this amount of time is very, very encouraging,” Lake Lure Town Manager Olivia Stewman said. From restoring the Lake Lure Dam to reopening public spaces like the beach, officials say visible improvements can be seen across the region. Still, Stewman noted that long-term recovery could take years.

Read more here  

3. Lake Lure Aiming for Spring 2026 Reopening - Watch the newscast here.

 

Lake Lure aiming for spring 2026 reopening

The Town of Lake Lure is hopeful it can reopen by next spring.

The announcement comes as the U.S. Army Corps of Engineers continues to remove debris and contaminated sediments from the lake.

They expect to complete work on the lake basin and shoreline by Oct. 31.

The town is also working to rebuild many facilities damaged by Helene.

Lake Lure to be fully restored by late spring 2026 after Hurricane Helene

 

 4. Lake Lure to be fully restored by late spring 2026 after Hurricane Helene

LAKE LURE, N.C. — Lake Lure officials announced a timeline for when the area will be reopened after Hurricane Helene devastated at area almost one year ago.

Watch the newscast here

Lake Lure to be fully restored by late spring 2026 after Hurricane Helene

 

Officials said they are looking to be fully restored by late spring 2026. The U.S. Army Corps of Engineers expects to complete work on the lake basin and shoreline by Oct. 31, with the lake scheduled to reach full capacity by May 1, 2026, according to town officials.

“The Town of Lake Lure is forever grateful to FEMA, the USACE, AshBritt, and the many local contractors and crew members who made this progress possible,” Mayor Carol Pritchett

said. “We could never have addressed the scale of destruction from Hurricane Helene without their remarkable support, expertise, and compassion.”

Helene, described as a once-in-a-thousand-year storm by officials, struck the western North Carolina community on Sept. 27, 2024. Since October 2024, restoration crews have worked 12-hour day shifts seven days a week in the recovery effort.

The Federal Emergency Management Agency and the Army Corps of Engineers have led the charge in restoring the community with help from AshBritt Environmental and local contractors. 

"Reopening Lake Lure will be more than a return to normal—it will be a symbol of resilience, unity, and the incredible power of partnership," Pritchett said. "This achievement will help drive the full recovery of Lake Lure and the greater Hickory Nut Gorge region."

 

FEMA funding not to be used for Lake Lure’s Flowering Bridge, officials say

The Town of Lake Lure says federal funding will not be used to replace the Flowering Bridge, which was destroyed during Hurricane Helene.

 

Note: There were a number of articles related to the FEMA Funding for the Flowering Bridge.  The Town of Lake Lure addressed this in a Press Release from the Town Manager.  

 

KEEP IT IN THE ROAD!

 

Memorial Highway (64/74) between Lake Lure and Chimney Rock is open.  NC Department of Transportation (NCDOT) has been repaving portions of 64/74 in Lake Lure this week. 

Repaving 64-74 in Lake Lure

Highway 64/74A Beyond Chimney Rock Village: Highway 64/74A heading West beyond Chimney Rock Village remains closed to the public at large. It is open to "locals", which is defined as those who live and work in the area. Please do not use this road if you do not have to, as contractors have to stop their work to allow for passage when cars go by, slowing the recovery process. 

NC DOT updates on Highway 64: A temporary road is expected to be open between Chimney Rock and Hendersonville was extended to June 30, 2027 (YES, 2027). For more information, visit NC DOT’s Drive NC link: https://drivenc.gov/?type=incident&id=715074      

Update from Gerton Fire and Rescue: "We would like to impress that these roads are for local traffic only. We have had a surge in tourists over the last few weeks. Please stay out of the gorge if you do not live there and let them work." Gerton Fire Chief.

Directions to Lake Lure from I-26: 

Proctor Road: The project is complete. The road will be open moving forward.  The next step is repaving the road but it will be passabile during this phase of the work.  Thank you to the residence for their patience as this work was completed. 

Lago Vista Road Extension: Town officials collaborated with Odom Engineering to solicit and review bids for the extension of Lago Vista Road, aimed at improving access to Chimney Rock State Park. The Town is currently working with state agencies to explore partnership opportunities to support the project.

Boys Camp Road Bridge: LaBella Associates are designing the Boys Camp Road Bridge.  The design is expected to be completed by the late fall.  Once the design is complete the project will go out for bid.

 

CELL TOWER UPDATES

 

For those who have experienced challenges with phone service in Lake Lure - crews were finally able to break ground for the new cell tower! 

  • The location of the cell tower will be off Boys Camp Road on the old campground property. 
  • The site and access road grading began 9/2/25. 
  • Crews began construction this week. 
  • Tillman Infrastructure is building the tower and will own it.
  • They will lease antenna space to cellular service providers and AT&T will be the primary provider.
  • Verizon has leased the next highest space and T-Mobile will be the third provider.
  • The antenna is expected to be in place this winter.

 

MORSE PARK TEMPORARILY CLOSED

 

To ensure the work can be completed safely and on schedule, Morse Park will be temporarily closed. 

  • We cannot provide a timeline for this project at this time, but weekly updates will be provided here.
  • The Town of Lake Lure understands the importance of Morse Park to our community, and we appreciate your patience during this temporary closure.
  • The East Entrance of Morse Park will be open for Lake Lure and Chimney Rock VIllage Commemoration Ceremony at the Gazebo on 9/27/25 at 11:00. 

 

LAKE LURE DAM

 

  • Reservoir Drain: The reservoir drain project at the dam has allowed the Town to lower the lake to 30 feet as planned for the ongoing lake restoration work.  The drain is closed at times if work is taking place behind the dam to ensure safety.  Otherwise, it is open to allow a flow of water in the river. 

  • Field Testing for Replacement Dam: Schnabel Engineering completed the field testing for the replacement dam.  The final report has been dubmitted to the NC Department of Envorinmental Quality Dam Safett Office for review and approval.   

  • Tainter Gate Repairs: Schnabel Engineering conducted an inspection of the Tainter gates. Based on their findings, the Town Council approved a work order for the design of necessary repairs, including seal repair.   Schnabel Engineering is developing the scope of work, which includes the design of repairs to the dam’s concrete ogee (allows for uncontrolled flow over the top of the reservoir) and the installation of new rubber seals along the base of the Tainter gates. This project will be completed when the lake comes back up a bit, in the winter of 2025-26.

  • Grant to Support Design for Replacement Dam: We hope to begin design work for the replacement dam in the fall of 2025. We are hoping to receive confirmation on a FEMA High Hazard Potential Dam (HHPD) Grant to support the cost of this project. We should receive a confirmation on this funding in the coming weeks.  

  • Boom: Schnabel is designing a boom for the dam area.

  • Recognition: We are also proud to share that the Town has been selected to receive the 2025 Southeast Regional Dam Safety Award from the Association of State Dam Safety Officials (ASDSO). This recognition highlights the Town’s efforts on the Low-Level Outlet Project, its proactive response to Hurricane Helene, and its ongoing commitment to securing funding for a long-term dam solution.

 

WATER AND SEWER SYSTEM 

 

West-end Sewer System: The work on the West End Sewer System Project began on 3/10/25 once easements were finally obtained by impacted property owners.  The West End Sewer System was destroyed by Hurricane Helene and was largely completed this week. The following properties impacted by the West End Sewer Project have restored sewer service:

Boys Camp Road properties: 109, 113, 160

Sea Wish Way: 114, 135, 137, 145, 186

Memorial Hwy: 3070, 3105, 3127, 3143, 3147

Town staff contacted property owners to inform them of the restoration. A few properties have laterals that run to the edge of our easement; those owners will need to work with a plumbing contractor to tie their service into the system.

For the remaining customers, the Town is awaiting the completed design for the line along Memorial Highway. All necessary materials are on hand and ready to be installed as soon as the design is received, aside from the manholes, which will be procured once the design is finalized.

Sewer Replacement Project: Town Officials meet regularly with LaBella Engineering to review current task orders and progress on the sewer replacement project. Upcoming phases for the sewer project were submitted to the NC Department of Environmental Quality (NC DEQ) for review in an Engineering Report/Environmental Information Document (ER/EID).  NCDEQ has provided initial comments and questions, which LaBella is actively addressing. In preparation for upcoming phases of the project, the Town has also begun communicating with several residents to discuss potential easement needs.

The Town continues to work closely with the North Carolina Division of Water Infrastructure (NC DWI) and neighboring communities to pursue a grant that will fund a study on the potential impacts and benefits of a regionalized sewer system.

Additionally, the Town is collaborating with NC DWI to secure supplemental State Revolving Fund (SRF) financing, which is expected to include principal forgiveness.

Sewer System Maintenance: Public Services continues to work to maintain the larger sewer system.  Planning and design work will be proceeding in Sunset Cove, Tryon Bay, Snug Harbor, and Grey Logs Cove in anticipation of future funding.  The Town has applied for FEMA funding to support restoration of the system.  We are awaiting a decision regarding this request and updates will be provided as new information becomes available.   

Mainline Sewer Repair: The Town is actively trying to address the mainline issue, it is not fully resolved, but there is enough flow that it is currently operational. 

Washburn Tank Cover Replacement: Successfully completed the replacement of 20 water tank system lid, improving system integrity and safety.  The Town has been working with LaBella Associates to design and replace the 20,000-gallon tank cover for the Washburn Tank. The Authorization to Construct was issued on December 7, 2023, following the Water Tank Reconditioning Plan approval on November 7, 2023.

  • Although the project experienced delays due to Tropical Storm Helene, progress has continued.
  • The engineer’s certification was issued, and a request for final approval was submitted to NCDEQ on June 17, 2025.
  • Water testing was completed and yielded satisfactory results.
  • Final approval from NCDEQ was issued on July 11, 2025, officially marking the project's completion.

Lift Station: The system is operational and online

Waste Water Treatment Plant: The Waste Water Treatment Plant (WWTP) is operational, but we have submitted a request to FEMA for a replacement treatment system. We are awaiting a decision regarding this request and hope to relocate the system out of the flood zone.

FEMA Public Assistance (PA) is working with the Town to move the permanent repairs for the Wastewater Treatment Plant (WWTP) forward as a Version 0 project, which allows the Town to receive funding for architectural and engineering (A&E) services.

  • A task order with LaBella was previously approved by Town Council, contingent upon FEMA funding.
  • Once this project is officially obligated, LaBella Associates will be able to proceed with the design work.

It is the Town's position—and that of the engineers at LaBella Associates, that the appropriate permanent repair for the WWTP is a full replacement of the facility, rather than piecemeal repairs to the existing plant, which is not feasible.

Utility Locate Responses: Responded to 26 utility locate requests through the 811 system, ensuring safe excavation and infrastructure protection across multiple work zones.

Are we applying for grants to assist with expenses? Yes!  LaBella Associates are working with Town officials to prepare an application for the Helene Recovery State Revolving Fund (SRF), which offers the potential for up to $5 million in principal forgiveness, if awarded. The SRF is a program that provides low-interest loans for water and wastewater infrastructure projects. 

Deep Water Ramp: The deep water ramp is being designed in the Rumbling Bald area. This will support various major infrastructure projects, but the primary focus is to support the sewer replacement project. 

 

PRIVATE WELLS

 

If you have a private well and lowering the lake has affected your well, then lake water may have been infiltrating your aquifer.

  • The first signs are sedimentation in your water, then air introduction to your system. 
  • The Town anticipates the lake will continue to be lowered for several more weeks. 
  • We do not currently have a date for refilling the lake as it is dependent upon the silt/sedimentation/debris removal being overseen by the USACE.  
  • It is recommended that individuals experiencing these indicators consult a well company.
  • Sedimentation can be filtered, but air usually means you need to dig a deeper well to retrieve water from a protected aquifer below the clay or rock layer.

The Town of Lake Lure consulted with the North Carolina Department of Environmental Quality regarding this matter to see if they could be of any assistance.  They provided the following link for individuals seeking financial assistance with their wells: Water Well Trust.  You may learn more about applying for this assistance here.

Additionally, here are resources for assistance with testing and disinfecting personal wells.

1)  Foothills Health District: Please click on the following link for Emergency Drinking Water Well Disinfection Procedures

     http://www.foothillshd.org/images/forms/4000/4001/FoothillsHealth_WellWa...

2)  Broad River Water Authority: 828-286-0640  https://www.ncbrwa.com/

3)  James & James Environmental Management, Inc.: 828-697-0063 https://www.facebook.com/jamesandjames1992/

 

CONTRACTOR INFORMATION

 

Only approved contractors may access properties from the lake, by boat or barge, but any contractor or property owner may work on lake structures (with permits) if accessing from land.  This includes sea wall construction or restoration (again, with required permits).   You may emailkmartin@townoflakelure.com"> kmartin@townoflakelure.com with any questions.

Click here for additional information on contractors.

 

DAMAGED LAKE STRUCTURES

 

The Community Development Department has created a map showing most of the seriously damaged lake structures, over 100 boathouses.  These are properties that the owners agree to the demo of the boathouse. If you have damages, be aware that you will need to contact the Community Development Department about permitting for repairs or replacement.  Permits are being issued and work is being done on lake structures now, but all work must be authorized. 

  • For property owners who signed up for the no-cost demolitions by the Army Corp, they are working on their plan now and we will notify you as we have more specific timing information. 
  • We have confirmed that, if you are signed up for the condemnation/removal program, they will be contacting you individually for a “right of entry” agreement prior to beginning the work.
  • Town officials are working with the USACE to determine their timeline for this process, likely in the winter months. 
  • Please contact Community Development Staff for more information about the Army Corp program, as well as your permitting, at kmartin@townoflakelure.com or 828-625-9983, x 135.

 

FINANCIAL SUPPORT/APPLICATIONS

 

The following chart illustrates the financial support the Town of Lake Lure is currently seeking, in addition to Federal and State Funding requests that have been made on behalf of the Town through our political representatives (disaster management planning experts) and Hager Strategic Solutions (lobbyist).  They are assisting the Town with post-disaster federal funding applications and requests to expedite our recovery process.

There are now 34 projects that have been submitted to FEMA for consideration of funding and the Town is awaiting their review and feedback.

8/13/25 update: Nine FEMA-funded projects have been obligated. The Town has received $2,325,171.92 for seven of these, and two additional reimbursements totaling $38,212.80 are pending. Delays persist for projects over $100,000, and staff have begun contacting elected officials to address these concerns. 

8/20/25 update: One additional project was obligated (totaling 10 obligated) and the total amount pending reimbursement is $783,697.92.

Several other projects are currently under review by FEMA. While the process continues to move slowly, we are seeing progress, and these projects are inching closer to obligation.

  • Diving Operations at the Dam ($700K range)
  • Flowering Bridge Demo: Version 0 - will have to argue costs. 
  • Community Center/Welcome Center: Came back at $160,000, which is far too low.
  • Marina Docks
  • Lake buoys and booms.

9/10/25 update: Newly received funding:

  • $13,255.75 – Category A: Dumpster rentals 
  • $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility
  • $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work

9/18/25 update: $2.8 million oblgated for Flowering Bridge Demo: Version 0 - As noted above, Town officials will have to argue costs. The $2.8 million currently obligated represents a preliminary estimate, intended to provide the Town with initial funds to cover demolition costs already incurred and to support efforts to develop accurate replacement cost estimates. The Town is actively pursuing discussions with FEMA to negotiate a fixed cost offer based on the true cost of replacement. It is the Town’s intention that these valuable funds be directed toward priority recovery projects that will strengthen and restore our critical infrastructure. Read here for additional details.

Organization

Funding Request

Status

State of NC-DEQ-Water

(Loan with potential forgiveness)

$3,000,000

Application under review

FEMA-Revenue Replacement

(Loan with potential forgiveness)

Up to $5,000,000

Financial data under review; additional data being provided

FEMA reimbursements

Up to $7,500,000

5/2/25 Update: 5 projects now obligated for a total of $3,224,564.61.

·$862,186.69 Received 4/25 for a Category A (Debris Removal)

5/18/25 Update: $754,185.81 (anticipated 5/25) for a Category B (Emergency Protective Measures) (payment received)

5/23/25 Update: Received a check for $65,390.00 for Category A Town Wide Vegetative Debris Removal from ROW and Public Property.

A new project was obligated for $118,323.67 for Category B Temporary Hydroelectric Plant Emergency Repairs. (payment received)

6/23/25 Update: Received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C); 

8/4/25 Update: Received $8,250 for Temporary Town Hall Facility (Category B);  Received $13,255.75 for Lake Lure Dumpster Rentals (Category A);

9/10/25 update: Newly received funding: $13,255.75 – Category A: Dumpster rentals; $28,531.78 – Category B: Temporary Relocation Costs – Town Hall Facility; $9,681.02 – Category F: Municipal Water Supply Damage – 100% Complete Work

DEQ-ARPA Reimbursement (non-storm related)

Up to $3,000,00

Submission under review

Private Donations

Up to $90,000

Deposited; being held for future disbursement under discretion of Town Council

Other Revenues and Payments from Insurance proceeds and claims

Up to $5,000,000

50% has been approved for release

1/7/25 Update: 50% received.

1/31/25 Update: $1.3 million insurance payment for damage to Town Hall. 

NC Treasurer Cash Flow Loan

$3,423,122.89

3/21/25 Update: Received   

6/23/25: The Town was offered an additional $2.8 million in cash flow funds from the State Treasurer.  A recommendation regarding this offer will be made to Town Council for consideration.

6/25/25: Town Council approved the loan.

7/29/25: Received a $2.8 million dollar loan disbursement this week from the NC Treasurer

 

MONETARY DONATIONS

 

Our community, along with many of our neighbors, has been devastated by the catastrophic flooding caused by Hurricane Helene. The Town of Lake Lure, NC is deeply grateful for the support our community has received.  We have had numerous requests to establish a mechanism for financial donations. Please click on the following link to donate to the Town of Lake Lure Storm Recovery Fund.  

https://www.paypal.com/ncp/payment/WXB6HYYE8Y5PJ

Additional options for monetary donations include the following: 

 

STORM RECOVERY ACCOMPLISHMENTS

 

Swift evacuation by first responders saving countless lives 9/27/24.

Countless rescues first responders during and following Hurricane Helene.

Coordination with the Rutherford County Emergency Management during and throughout the storm.

Dam assessment and stabilization immediately following the storm event 9/27/24-9/29/24.

Communication with the Rutherford County EOC and FEMA for recovery immediately following the storm.

Coordination with volunteer groups to provide hot meals, shower services, restrooms, and handwashing stations in strategic locations by 10/1/24. Christian Aid Ministries served 8,080 hot meals and assisted 43 homeowners with clean-up of their homes and property.  There were 164 volunteers and they spent 2,457 hours assisting our community!

Creation of donation stations to disseminate supplies throughout town by 10/1/24. 

Cleared Highways and Town roads within days of the storm.

Restoration of water service throughout Town with water quality testing allowing Boil Advisory lifted 10/14/24 and 10/16/24 respectively.

Rapid repair of power services throughout Town by Duke Power and REMC.  

Establishment of temporary communications systems through Starlink (10 systems) and Cell on Wheels with AT&T and Verizon 10/16/24.

Replacement of fiber to re-establish internet and cell service to the area 10/18/24. 

Repair to the left abutment of the Dam by 10/27/24 with 2,494.64 tons of material securing the area.

Army Corps of Engineers contract signed with AshBritt to oversee lake debris and silt/sedimentation removal during a 160 day period of performance beginning 10/28/24.  Debris removal began 11/4/24.

Emergency repairs to the sewer system completed, allowing "no flush order" to be lifted for most on 10/28/24.

Reopening of the Dam Bridge on Buffalo Shoals Road on 10/31/24.

Dittmer Watts Nature Trails and a portion of the Green Space reopened on 11/19/24.

Pressure Reducing Valve Construction in Lake Lure Town Center successfully completed 11/22/24.

The Boys Camp Road Temporary Bridge was completed 11/26/24.

As of 1/23/24, Over 32,782 CY of debris were removed from the right of way, 27,669 tons of sediment and silt have been removed from Town and the Parks, 24,558 cubic yards (CY) of debris have been removed from the Lake.

1/10/25: Burnt Ridge Landslide repair completed.

1/7/25: 50% of insurance payments received.

1/22/25: Contracted with lobbyist Hager Strategic Solutions (lobbyist). 

1/22/25: Proclamation to open Chimney Rock State Park as soon as possible to bring in tourism to the area and strengthen the economy.

1/31/25: Culvert repair on Hummingbird Cove completed.

1/31/25: $1.3 million insurance payment received for damage to Town Hall. 

2/11/25: Waste Water Treatment Plant is now operational.  Repaired 3 water leaks throughout the water system

2/14/25: Storm drain box culvert repaired at corner of Memorial Hwy and Charlotte Dr

2/19/25: Youngs Mountain Trail landslide repaired

2/21/25: Green Space drainage repairs completed, grass replanted, and dry creek beds put into place.

2/28/25: The Town of Lake Lure and all those in areas code 28746 are eligible to apply for a free option for debris removal program through the USACE.

3/7/25: Debris removed from Morse Park trails and grass replanted in that area.

3/14/25: FEMA approval of the mission assignment for Lake Surface Debris, silt, and sedimentation removal through FEMA and the US Army Corps of Engineers.

3/18/25: Community Forum held with FEMA, USACE at The Lakeside Terrace with approximately 200 attendees.

3/18/25: United Way presented Fire Chief Dustin Waycaster a check for $50,000 for a new heart monitor for Firefights/AMTs.

3/27/25: Reservoir Drain Valve Installation complete.

4/24/25: 371 +/- boats that have been removed from the lake.

4/25/25: Reopened the East entrance to Morse Park.

5/2/25: $862,186.69 Received 4/25 for a Category A (Debris Removal)

5/11/25: $754,185.81 Received for a Category B (Emergency Protective Measures)

6/12/25: New seawall completed at the Lake Lure Gazebo

6/13/25: New pavers replaced broken and missing pavers in the Morse Park walkway and in front of the Lake Lure Beach. 

6/17/25: The Lake Lure Beach was replenished with fresh sand.  

6/23/25:  The Town received a check for the Boys Camp Road Bridge Damage: $503,580 (Category C)

6/25/25: Cash flow loan approved for $$2.8 million.

6/27/25: Downslide repaired on Angler's Way. 

7/21/25: Repairs on Boys Camp Road completed.

7/21/25: Debris and silt/sedimentation removal from the Rumbling Bald Beach and Marina are complete.

7/28/25: Town Hall relocated to temporary office space in The Landings. The official opening date for the public is 8/1/25.

7/28/25: The Town received the $2.8 million loan disbursement this week from the NC Treasurer.

8/7/25:  Received $8,250 from FEMA for Temporary Town Hall Facility (Category B);  Received $13,255.75 from FEMA for Lake Lure Dumpster Rentals (Category A).

8/13/25: Silt/sedimentation removal began in Washburn Marina and coves around the lake, like Tryon Bay.

8/20/25: Asheville Tennis Association presented the Town of Lake Lure with a check for $19,000 to help rebuild our future tennis/pickleball courts.

8/20/25: The Lake Lure Fire Department received a $50,000 grant for support in upgrading Lake Lure Station II.

8/30/25: West end Sewer System largely restored. 

9/10/25:  FEMA funding received: $13,255.75 for Dumpster rentals, $28,531.78 for Temporary Relocation Costs – Town Hall Facility, $9,681.02 for Municipal Water Supply Damage

9/19/25: Proctor Road restoration project complete.

ONGOING

  • Emergency repairs to the sewer system.
  • Constant removal of silt, sedimentation, and debris from the lake and roadways.
  • Removal of condemned boathouses and personal property debris removal.
  • Town officials are working to develop a comprehensive plan for future prosperity in the Town of Lake Lure.   

 

WHAT’S OPEN IN THE TOWN OF LAKE LURE!

 

Welcome to Lake Lure

Lake Lure Welcomes Visitors Back As Recovery Continues: While visitors should be mindful of ongoing recovery efforts, several local businesses and recreation areas have reopened.  There are a number of attractions that are open in the area. Lake Lure hotels, lodges, bed & breakfasts, and our amazing restaurants are open for business!  Our local businesses greatly appreciate your patronage!  Please visit the area and encourage others to visit as well. 

Download the 2025 Travel Guide here.  

Please visit the Local Restaurant Guide

And here are some of the amenities that are currently open to the public.  

  • Morse Park Walkway and the Lake Lure Gazebo (temporarily closed during silt removal in Marina Cove.)
  • Dittmer-Watts Nature Trails
  • Lake Lure Green Space
  • Pool Creek Picnic Park
  • Youngs Mountain
  • Rumbling Bald Golf Courses
  • Chimney Rock State Park – Rumbling Bald Access
  • Chimney Rock State Park – Now open daily by reservation - Click here to reserve your tickets!

Additionally, horseback riding is available in the area along with zip lining, escape rooms, a candy cabin, and so much more!

New Playground Planned: The Town has been approved for a grant for a replacement playground, which will be placed in Morse Park in October, just inside the walkway to the Gazebo.  October 13-15, 2025 will be volunteer prep and building days. Please join us!   

Buffalo Creek Park/Weed Patch Mountain Trail/Upper Boulders Trail: Ongoing work is also taking place at Buffalo Creek Park, Weed Patch Mountain, and the Upper Boulder Trails by the National Guard, Carolina Climbers Coalition, Rutherford Outdoor Coalition, EcoForesters, and AmeriCorps. We cannot thank them enough for their time and support!  Update 6/17/25: Progress continues to be made on Upper Boulders Trail, and a small section may be opening soon. The Town will receive a grant of $50,000 to assist with restoration.  Please stay tuned for updates!

Upcoming Events:

 

COMPREHENSIVE PLAN

 

The Town's Comprehensive Planning process is underway. To help guide this important effort, an 11-member steering committee was established. In addition to advising on the overall process, committee members will help promote community engagement, review draft materials, and serve as a vital connection between the public, planning staff, and Town leadership.

The public will have multiple opportunities to participate in shaping the plan, including through surveys, community input sessions, and town hall meetings—anticipated to begin in the fall.  PLease stay tuned. 

 

QUESTIONS/SUGGESTIONS

You may review previous Storm Recovery Updates in Town News at www.townoflakelure.com

For questions or suggestions, please email Communications@townoflakelure.com